Permanent Occupancy | | 5/5/2005 | 5/5/2005 | | DONE |
|
|
|
|
DOC - Permit Finaled | | | 5/5/2005 | | DONE |
|
|
|
|
BLD-Final | 5/4/2005 | 5/4/2005 | 5/4/2005 | P | PASS |
Bob Archibald
|
|
|
Ok for final.
|
Code Occupancy Approval | 4/29/2005 | 4/29/2005 | 4/29/2005 | P | PASS |
Dena Gambrel
|
|
|
All conditions met. Signed off. 4/29/2005 12:03:29 PM
|
FIRE-Final Inspection | 4/26/2005 | 4/26/2005 | 4/26/2005 | P | PASS |
Forrest France
|
|
|
Fire life safety finaled.
|
BLD-Conference | 4/22/2005 | 4/22/2005 | 4/22/2005 | P | PART |
Bob Archibald
|
|
|
Not all signatures obtained. Will meet with Richard next week.
|
FIRE-Final Inspection | 4/18/2005 | 4/19/2005 | 4/19/2005 | A | FAIL |
Forrest France
|
|
|
Fail life safety inspection. Need current tag on fire extinguisher, install lever hardware on backdoor, install lever hardware on exterior enclosure gate facing Overland Rd., adjust hardware on one interior dog gate. Hardware type and height on three i
|
BLD-Framing/Rough-in | 4/1/2005 | 4/1/2005 | 4/1/2005 | P | PASS |
Tom Arcoraci
|
|
|
Framing approved for cover except where waterlines for relocation of bath sink, will need to remain uncovered for plumbing inspection. Wall bracing and bearing for storage shed approved as per engineered details.
|
BLD-Conference | 3/22/2005 | 3/22/2005 | 3/22/2005 | A | FAIL |
Bob Archibald
|
|
|
CN issued requiring final occupancy within 30 days.
|