Code Occupancy Approval | | | 8/15/2007 | | PASS |
|
|
|
LANDSCAPE NOW FINISHED OK FOR FINAL AND RELEASE OF BOND.
|
BLD-Final | 2/13/2007 | 2/14/2007 | 2/15/2007 | P | PART |
Mike Jordan
|
|
|
troy; Phone #: ###-#### Internet Inspection Request from: Patricia Smit. All issues have been resolved except for issues noted on final Aff. letter from special insp. agency. Noted items must be resolved and approved by structural engineer prior to perm occ.
|
FIRE-Final Inspection | 2/14/2007 | 2/14/2007 | 2/14/2007 | P | PASS |
Troy Cobbley
|
|
|
Life safety finaled
|
BLD-Final | 2/8/2007 | 2/9/2007 | 2/9/2007 | A | PART |
Mike Jordan
|
|
|
Temp occ granted. Needs to complete some firecaulking on the 3rd and 4th floors, fix grab bars in rooms 219, 104 and pool restroom. Complete firecauling at front desk area. Install safety glazed windows @ stairtower. Will have repaired in two weeks as per contractor.
|
FIRE-Final Inspection | 2/7/2007 | 2/8/2007 | 2/9/2007 | A | PART |
Troy Cobbley
|
|
|
Temporary occupancy given until small list of items has been corrected. Per the contractor the inspection is to be called in on Monday. List is with the sign off card.
|
BLD-Final | 2/8/2007 | 2/8/2007 | 2/8/2007 | P | CANC |
Mike Jordan
|
|
|
|
Code Occupancy Approval Temp | 2/8/2007 | 2/8/2007 | 2/8/2007 | P | DONE |
Scott M.Brown
|
|
|
BOND NEEDED FOR $60,000 LANDSCAPE REF DRH03-00159.
|
BLD-Final | 2/7/2007 | 2/8/2007 | 2/8/2007 | A | NR |
Mike Jordan
|
|
|
Spoke with contractor on phone. Still needs to post bond and needs life/safety.
|
BLD-Final | 2/7/2007 | 2/7/2007 | 2/7/2007 | P | CANC |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 2/7/2007 at 10:06:37 AM. Contact: ###-####. Note ready. rescheduled for the am. 2-8-07.
|
BLD-Framing/Rough-in | 1/23/2007 | 1/24/2007 | 1/24/2007 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 1/23/2007 at 1:34:07 PM. Contact: ###-####. grid appears ok fire stop conduits in kit and west end of corr
|
BLD-Conference | 1/22/2007 | 1/22/2007 | 1/22/2007 | P | DONE |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 1/22/2007 at 11:15:37 AM. Contact: ###-####.
|
FIRE-Conference | 1/17/2007 | 1/18/2007 | 1/18/2007 | A | DONE |
Troy Cobbley
|
|
|
I spoke to troy about the fire hydrant located in the southwest corner of the property. It can be located on the outside of the fence but there needs to be 3' of clearance around it. Also the gates must be able to swing into the property so that the hydrant is not blocked.
|
BLD-Framing/Rough-in | 1/15/2007 | 1/16/2007 | 1/16/2007 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 1/15/2007 at 9:48:07 AM. Contact: ###-####. Ceiling grid at commercial laundry room and conferance room, 1st. floor.
|
BLD-Conference | 1/2/2007 | 1/3/2007 | 1/3/2007 | A | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 1/2/2007 at 12:38:26 PM. Contact: ###-####. Ceiling grid insp in office at kitchen and went over cicsca 3 to 4 specs and what would be required.
|
BLD-Conference | 12/19/2006 | 12/19/2006 | 12/19/2006 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 12/19/2006 at 7:32:06 AM. Contact: ###-####. Inspected firecaulking at lids abovegrids on all floors. Need ceiling plan from architect for grid system. Elec. room penetrations not yet done on all floors.
|
BLD-Conference | 12/18/2006 | 12/18/2006 | 12/19/2006 | P | CANC |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 12/18/2006 at 8:24:44 AM. Contact: ###-####.
|
FIRE-Conference | 11/8/2006 | 11/9/2006 | 11/9/2006 | A | NH |
Forrest France
|
|
|
Scheduled by a contractor via Hello! on 11/8/2006 at 11:35:12 AM. Contact: ###-####. Contractor not available.
|
BLD-Framing/Rough-in | 9/20/2006 | 9/20/2006 | 9/20/2006 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 9/20/2006 at 10:29:50 AM. Contact: ###-####. Grid for hardlid in lobby area ok to rock.
|
BLD-Framing/Rough-in | 9/18/2006 | 9/18/2006 | 9/18/2006 | P | NR |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 9/18/2006 at 7:41:50 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 9/12/2006 | 9/12/2006 | 9/12/2006 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 9/12/2006 at 10:48:33 AM. Contact: ###-####. Fire control panel has been boxed out in one hour wall at kitchen area.
|
BLD-Framing/Rough-in | 9/8/2006 | 9/8/2006 | 9/8/2006 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 9/8/2006 at 10:03:54 AM. Contact: ###-####. 1st floor corridor lid, north and south wings. Majority of firecaulking complete. Areas left will be accessible thru hatches or soft grid.
|
BLD-Framing/Rough-in | 9/6/2006 | 9/7/2006 | 9/7/2006 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 9/6/2006 at 7:03:24 PM. Contact: ###-####. 1st floor corridor lid, ok to start rock, will leave areas open were fire caulk not complete. ok to rock kitchen area and back offices. Still needs to box around fire panel at 1 hr. wall.
|
BLD-Framing/Rough-in | 9/5/2006 | 9/6/2006 | 9/6/2006 | P | FAIL |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 9/5/2006 at 10:52:27 AM. Contact: ###-####. Needs to complete the fire caulking at the 1st floor corridor lids. not ok to cover.
|
BLD-Framing/Rough-in | 9/4/2006 | 9/5/2006 | 9/5/2006 | A | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 9/4/2006 at 9:20:51 AM. Contact: ###-####. ok to insul. kitchen and back office areas. Needs to rock around fire control panel at 1 hr. wall.
|
BLD-Framing/Rough-in | 9/1/2006 | 9/1/2006 | 9/1/2006 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 9/1/2006 at 11:02:03 AM. Contact: ###-####. 1st floor lids ok to rock, rooms only. Ceiling grid in pool room ok, ok to cover corridor betwwen pool room and excercise room.
|
BLD-Framing/Rough-in | 9/1/2006 | 9/1/2006 | 9/1/2006 | A | CANC |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 9/1/2006 at 7:06:31 AM. Contact: ###-####. canc by contractor.
|
BLD-Framing/Rough-in | 8/30/2006 | 8/31/2006 | 8/31/2006 | P | FAIL |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/30/2006 at 3:57:17 PM. Contact: ###-####. 1st floor lids, south wing, rooms only. Needs to complete fire caulking of penetrations at ceiling assembly.
|
BLD-Framing/Rough-in | 8/29/2006 | 8/29/2006 | 8/29/2006 | A | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/29/2006 at 7:06:52 AM. Contact: ###-####. ok to insul. corridor between pool room and excercise room.
|
BLD-Framing/Rough-in | 8/25/2006 | 8/25/2006 | 8/25/2006 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/25/2006 at 9:23:32 AM. Contact: ###-####. insul. at mech room, 1st floor.
|
BLD-Framing/Rough-in | 8/22/2006 | 8/22/2006 | 8/22/2006 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/22/2006 at 7:37:56 AM. Contact: ###-####. ok to rock 2hr wall at mech. room and reinstall furr out wall.
|
BLD-Framing/Rough-in | 8/18/2006 | 8/21/2006 | 8/21/2006 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 8/18/2006 at 2:49:55 PM. Contact: ###-####. 2nd floor drops ok
|
BLD-Other | 8/16/2006 | 8/17/2006 | 8/17/2006 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 8/16/2006 at 11:25:26 AM. Contact: ###-####. insulation ok at conf room to bath room
|
BLD-Framing/Rough-in | 8/11/2006 | 8/11/2006 | 8/11/2006 | A | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/11/2006 at 7:15:22 AM. Contact: ###-####. ok to rock 3rd floor corridor lid, north and south wings. ok to cover pool room, excersizeroom. ok to oneside womens restroom and business center and insul. Need to verify putty pads at business center. ok to insul. mech room on first floor, but needs to remove furr out wall tro install insul. and 2 layers of 5/8 type x for 2 hour seperation wall.
|
BLD-Framing/Rough-in | 8/10/2006 | 8/10/2006 | 8/10/2006 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/10/2006 at 7:10:44 AM. Contact: ###-####. 3rd floor corridor ceilings, north and south wings. needs to patch holesand fire caulk conduits. Condiuts at grid areas and not hardlid.
|
BLD-Framing/Rough-in | 8/8/2006 | 8/8/2006 | 8/8/2006 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/8/2006 at 9:03:53 AM. Contact: ###-####. 4th floor corridor, north and south wings, ok to rock lid. soth wing elev. shaft insul. ok.
|
BLD-Framing/Rough-in | 8/7/2006 | 8/7/2006 | 8/7/2006 | P | PASS |
Mike Jordan
|
|
|
1st floor, south wing, insulation at rooms. ok to cover rooms.
|
BLD-Framing/Rough-in | 8/7/2006 | 8/7/2006 | 8/7/2006 | A | CANC |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/7/2006 at 7:20:21 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 8/4/2006 | 8/4/2006 | 8/4/2006 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/4/2006 at 7:55:19 AM. Contact: ###-####. ok to rock lids at 3rd floor rooms. ok to insulate stairtowers and elevator shafts. still needs to complete work at 4thfloor corridor lid prior to rocking. ok to rock lid and walls at pool room.
|
BLD-Framing/Rough-in | 8/3/2006 | 8/3/2006 | 8/3/2006 | A | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/3/2006 at 6:50:21 AM. Contact: ###-####. ok to rock lids at guest laundry and corridor between lobby and north wing. Missing hardware at pool and excersise room at roof framing.
|
BLD-Framing/Rough-in | 8/1/2006 | 8/2/2006 | 8/2/2006 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/1/2006 at 4:33:43 PM. Contact: ###-####. Intereior side of north wing ele. shaft. ok to insul.
|
BLD-Framing/Rough-in | 7/31/2006 | 8/1/2006 | 8/1/2006 | A | FAIL |
Mike Jordan
|
|
|
3rd floor rooms, north wing, hard lid frame. Frame ok, needs to complete all firecaulking at envelope penetrations. do not cover.
|
BLD-Framing/Rough-in | 7/28/2006 | 7/31/2006 | 7/31/2006 | P | CANC |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 7/28/2006 at 2:03:04 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 7/27/2006 | 7/27/2006 | 7/27/2006 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 7/27/2006 at 10:45:20 AM. Contact: ###-####. ok to insulate 1st floor, south wing.
|
BLD-Framing/Rough-in | 7/26/2006 | 7/26/2006 | 7/26/2006 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 7/26/2006 at 7:02:42 AM. Contact: ###-####. 1st floor norh wing insul ok. ok to cover. framing insp on 1st floor south wing, needs to add solid blocking behind floor to floor straps.
|
BLD-Framing/Rough-in | 7/20/2006 | 7/20/2006 | 7/20/2006 | P | CANC |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 7/20/2006 at 8:56:23 AM. Contact: ###-####. contractor called and cancelled insp.
|
BLD-Framing/Rough-in | 7/18/2006 | 7/18/2006 | 7/18/2006 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 7/18/2006 at 8:02:01 AM. Contact: ###-####. 1st floor framing, north wing.
|
BLD-Framing/Rough-in | 7/14/2006 | 7/14/2006 | 7/14/2006 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 7/14/2006 at 7:10:44 AM. Contact: ###-####. 2nd floor south wing insul ok to cover. 1st floor framing, solid blocking needed behind straps, repair 4x6 post, cout floor joist, strap bottom plates. missing putty pads on elec. boxes.
|
BLD-Framing/Rough-in | 7/10/2006 | 7/11/2006 | 7/11/2006 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 7/10/2006 at 4:16:04 PM. Contact: ###-####. insul. 2nd floor rooms, north wings.
|
BLD-Framing/Rough-in | 7/10/2006 | 7/10/2006 | 7/10/2006 | P | FAIL |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 7/10/2006 at 7:10:24 AM. Contact: ###-####. straps for dragtrusses not installed, roof framing for poolroom.
|
BLD-Framing/Rough-in | 7/5/2006 | 7/5/2006 | 7/5/2006 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 7/5/2006 at 7:49:12 AM. Contact: ###-####. roof framing at lobby area. ok to rock ceiling.
|
BLD-Framing/Rough-in | 6/29/2006 | 6/29/2006 | 6/29/2006 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 6/29/2006 at 10:39:36 AM. Contact: ###-####. 2nd floor, north and south wings, allframing issues have been repaired. Putty pads installed. ok to insulate rooms.
|
BLD-Framing/Rough-in | 6/28/2006 | 6/28/2006 | 6/28/2006 | P | FAIL |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 6/28/2006 at 7:35:10 AM. Contact: ###-####. 2nd floor, north and south wings. work not completed.
|
FIRE-Conference | 6/27/2006 | 6/27/2006 | 6/27/2006 | P | DONE |
Troy Cobbley
|
|
|
I notified the contractor the the cut-ins for the fire extinguisher cabinets in the corridor walls appear to be too low.
|
BLD-Framing/Rough-in | 6/27/2006 | 6/27/2006 | 6/27/2006 | P | FAIL |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 6/27/2006 at 7:31:59 AM. Contact: ###-####. 2nd floor, southwing. Needs to repair cut trusses shafts, installl straps on top plates and is missing puttypads on elec. boxes. Gave ok to oneside framing at concealed locations in lobby area so that insul can be installed.
|
BLD-Framing/Rough-in | 6/26/2006 | 6/26/2006 | 6/26/2006 | P | FAIL |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 6/26/2006 at 7:52:30 AM. Contact: ###-####. 2nd floor,north wing. Needs to supply an approved fix and fix all fllor joist that have been cut or notched. Needs to install straps on top plates and repair studs that have been cut. Also needs to repair shaft at northend rooms. ok to insul. walls.
|
BLD-Framing/Rough-in | 6/21/2006 | 6/21/2006 | 6/21/2006 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 6/21/2006 at 8:02:57 AM. Contact: ###-####. Insul. in 3rd floor rooms south wing. ok to rock walls
|
BLD-Framing/Rough-in | 6/20/2006 | 6/20/2006 | 6/20/2006 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 6/20/2006 at 6:40:21 AM. Contact: ###-####. Reinspected 4th floor rooms, north and south wings. All penetrations were firecaulked, radiation dampers installed at one hour ceiling wall assembly. Fatggrid ok. ok to hang rock.
|
BLD-Framing/Rough-in | 6/16/2006 | 6/16/2006 | 6/16/2006 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 6/16/2006 at 8:08:47 AM. Contact: ###-####.4th floor north and south wing rooms, inspected fat grid for shhet rock lid and firecaulking of penetrations above lid. Noted that not all penetrations are completed and that 4 vent fans are required to have radiation dampers at 1 hour ceiling assembly. ok to start sheet rocking in areas that are completed.
|
BLD-Framing/Rough-in | 6/15/2006 | 6/15/2006 | 6/15/2006 | P | NR |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 6/15/2006 at 7:57:53 AM. Contact: ###-####. Needs to complete firecaulking of penetrations prior to inspecting ceiling grid.
|
BLD-Framing/Rough-in | 6/12/2006 | 6/13/2006 | 6/13/2006 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 6/12/2006 at 7:24:33 AM. Contact: ###-####.ok to hang rock at rooms 3rd floor northwing. firecaulking and puttypads installed. ok to insulate rooms at 3rdfloor south wing.
|
BLD-Framing/Rough-in | 6/12/2006 | 6/12/2006 | 6/12/2006 | P | DEFR |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 6/12/2006 at 7:24:33 AM. Contact: ###-####.tue 6/13/06 450
|
BLD-Framing/Rough-in | 6/7/2006 | 6/7/2006 | 6/7/2006 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 6/7/2006 at 6:48:30 AM. Contact: ###-####. 3rd floor, south wing rooms. ok to insulate ceilings only. Needs to complete install of putty pads.
|
BLD-Framing/Rough-in | 6/1/2006 | 6/2/2006 | 6/2/2006 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 6/1/2006 at 2:43:58 PM. Contact: ###-####. 3rd floor, north wing, ok to insulate ceilings in rooms.
|
BLD-Framing/Rough-in | 5/24/2006 | 5/24/2006 | 5/24/2006 | P | PASS |
Mike Jordan
|
|
|
All items on 3rd floor north wing have been resolved. ok to insulate walls.
|
BLD-Framing/Rough-in | 5/23/2006 | 5/24/2006 | 5/24/2006 | A | CANC |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 5/23/2006 at 4:38:41 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 5/22/2006 | 5/23/2006 | 5/23/2006 | A | FAIL |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 5/22/2006 at 4:55:30 PM. Contact: ###-####.Needs to complete all fire caulking of penetrations at wall and floor ceiling assemblies 3rd floor North wing. Strap top plate 3rd floor north wing. Repair shaft at 3rd floor north wing.
|
BLD-Framing/Rough-in | 5/18/2006 | 5/19/2006 | 5/19/2006 | A | CANC |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 5/18/2006 at 3:49:20 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 5/18/2006 | 5/18/2006 | 5/18/2006 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 5/18/2006 at 7:39:38 AM. Contact: ###-####. roof framing south wing.
|
BLD-Framing/Rough-in | 5/15/2006 | 5/15/2006 | 5/15/2006 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 5/15/2006 at 7:02:59 AM. Contact: ###-####. 4th floor, north and south wings, ok to insul. rooms in south wings, north wing almost complete.
|
BLD-Framing/Rough-in | 5/10/2006 | 5/10/2006 | 5/10/2006 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 5/10/2006 at 7:54:55 AM. Contact: ###-####. Room 420 ok.
|
BLD-Framing/Rough-in | 5/8/2006 | 5/9/2006 | 5/9/2006 | A | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 5/8/2006 at 2:47:22 PM. Contact: ###-####. 4th floor, north wing corridor and rooms. ok to rock corridor lid, insulate rooms, except for room #420 and elevator and stairway lobby.
|
BLD-Framing/Rough-in | 5/4/2006 | 5/4/2006 | 5/4/2006 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 5/4/2006 at 8:45:31 AM. Contact: ###-####. ok to rock lids of elec room on 1st 2nd and 3rd fllors. All roof framing issues have been resolkved. ok to insulate corridor lid at 4th floor and corridor walls.
|
BLD-Framing/Rough-in | 5/2/2006 | 5/3/2006 | 5/3/2006 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 5/2/2006 at 4:34:35 PM. Contact: ###-####. Roof framing north wing, Needs to add hangers to girder trusses to support joists Needs to complete fire caulking at penetrations below walkway, and puuty pad elec. boxes. also needs to complete fire caulking as per listing on floor ceiling penetrations at elec. rooms on floors 1 to 3 prior to rocking the lids.
|
BLD-Framing/Rough-in | 5/1/2006 | 5/2/2006 | 5/2/2006 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 5/1/2006 at 4:05:46 PM. Contact: ###-####. 2nd floor shafts, north wing.
|
FIRE-Conference | 5/1/2006 | 5/1/2006 | 5/1/2006 | P | DONE |
Troy Cobbley
|
|
|
I spoke to the general contractor about getting the damaged fire hydrant that is located in the southeast corner of the project repaired as soon as possible. He stated that he had already started the process.
|
BLD-Framing/Rough-in | 4/24/2006 | 4/25/2006 | 4/25/2006 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 4/24/2006 at 4:06:40 PM. Contact: ###-####. Shear nailing on corridors at 1st 2nd 3rd and fourth floors.
|
BLD-Framing/Rough-in | 4/17/2006 | 4/17/2006 | 4/17/2006 | A | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 4/17/2006 at 7:14:28 AM. Contact: ###-####. 2nd floor, south wing vent shaft walls
|
BLD-Conference | 4/13/2006 | 4/13/2006 | 4/13/2006 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 4/13/2006 at 10:02:32 AM. Contact: ###-####. Discussed enclosure for fire dampers from floor to floor.
|
BLD-Other | 4/10/2006 | 4/10/2006 | 4/10/2006 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 4/10/2006 at 9:54:36 AM. Contact: ###-####. insulation behind shaft walls.
|
BLD-Conference | 4/4/2006 | 4/4/2006 | 4/4/2006 | P | DONE |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 4/4/2006 at 8:22:19 AM. Contact: ###-####. Received and reviewed UL listings for rated penetrations with plumber. Also noted to contractor that elec. and mech. contractors need to supply UL listings. Also discussed other rated issues with contactor.
|
BLD-Framing/Rough-in | 3/30/2006 | 3/30/2006 | 3/30/2006 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 3/30/2006 at 7:46:52 AM. Contact: ###-####. Roof nailing and mansard.
|
FIRE-Conference | 3/16/2006 | 3/16/2006 | 3/16/2006 | P | DONE |
Troy Cobbley
|
|
|
The wet stand pipes have been installed as dry temporarily with dave hannimans approval. Signage with gpm and psi requirements have been placed at the fdc. The standpipes are to be converted to wet when the building is enclosed and heated. Work can now continue on the fourth floor and above.
|
FIRE-Conference | 3/15/2006 | 3/15/2006 | 3/15/2006 | P | DONE |
Troy Cobbley
|
|
|
I left a stop work notice for all work on the 4th floor and above until standpipes have been installed per the fire dept. review comment #49.
|
BLD-Framing/Rough-in | 2/21/2006 | 2/21/2006 | 2/21/2006 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 2/21/2006 at 9:32:45 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 1/20/2006 | 1/20/2006 | 1/20/2006 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 1/20/2006 at 7:41:54 AM. Contact: ###-####. Shear nailing on exterior west wall of north wing, 2nd to 4th floors.
|
BLD-Framing/Rough-in | 12/30/2005 | 12/30/2005 | 12/30/2005 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 12/30/2005 at 11:13:44 AM. Contact: ###-####. 1st to 2nd floor shear nailing and floor to floor straps at exterior walls north and south wings. Also shear nailing on exterior walls at pavillion.
|
BLD-Concrete | 11/21/2005 | 11/22/2005 | 11/22/2005 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 11/21/2005 at 3:02:54 PM. Contact: ###-####. 3rd floor decking at corridors. Also inspected reinforcement for pool, which is under a different permit.
|
BLD-Framing/Rough-in | 11/14/2005 | 11/15/2005 | 11/15/2005 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 11/14/2005 at 8:34:16 AM. Contact: ###-####. Interior shear at north wing first floor.
|
BLD-Other | 10/26/2005 | 10/27/2005 | 10/27/2005 | A | FAIL |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/26/2005 at 3:49:38 PM. Contact: ###-####. need engineer to resolve steel cross beam bolt conections/ arch to address ledger angle and flutes to maintain fire rating.
|
BLD-Aging Inspection | 10/11/2005 | 10/11/2005 | 10/11/2005 | | PASS |
Jim Storey
|
|
|
wip
|
BLD-Other | 8/9/2005 | 8/11/2005 | 8/11/2005 | A | PASS |
Jim Storey
|
|
|
job conf. 900 am on site.
|
BLD-Other | 8/9/2005 | 8/11/2005 | 8/11/2005 | A | DONE |
Mike Jordan
|
|
|
900 am on site job meeting
|
BLD-Concrete | 8/9/2005 | 8/10/2005 | 8/10/2005 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 8/9/2005 at 4:36:03 AM. Contact: ###-####. placed w/si
|
BLD-Concrete | 8/9/2005 | 8/9/2005 | 8/9/2005 | A | FAIL |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/9/2005 at 4:35:22 AM. Contact: ###-####.Welded wire mesh not being adequtley lifted during concrete placement, on ground in some cases. concrete dobees should be used to gain proper clearance. reinforcement not properly tied into place at grade beams, reinforcement is being "wet stabbed" Concrete being placed is to "wet" 10 and 11 inch slumps as per special inspector.
|
BLD-Concrete | 8/5/2005 | 8/8/2005 | 8/8/2005 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 8/5/2005 at 2:44:37 PM. Contact: ###-####. slab on grade ok per plan.
|
BLD-Foundation | 7/19/2005 | 7/20/2005 | 7/20/2005 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 7/19/2005 at 3:18:33 PM. Contact: ###-####.placed w si
|
BLD-Footing | 7/13/2005 | 7/14/2005 | 7/14/2005 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 7/13/2005 at 11:52:20 AM. Contact: ###-####.si
|
BLD-Foundation | 7/12/2005 | 7/12/2005 | 7/12/2005 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 7/12/2005 at 7:09:25 AM. Contact: ###-####.
|
BLD-Foundation | 7/6/2005 | 7/7/2005 | 7/7/2005 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 7/6/2005 at 3:17:42 PM. Contact: ###-####.pwsi
|
BLD-Footing | 7/6/2005 | 7/7/2005 | 7/7/2005 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 7/6/2005 at 3:17:05 PM. Contact: ###-####.pwsi
|
BLD-Foundation | 7/1/2005 | 7/5/2005 | 7/5/2005 | A | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 7/1/2005 at 2:28:46 PM. Contact: ###-####.
|
BLD-Footing | 7/1/2005 | 7/5/2005 | 7/5/2005 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 7/1/2005 at 2:29:24 PM. Contact: ###-####.
|
BLD-Foundation | 6/29/2005 | 6/30/2005 | 6/30/2005 | A | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 6/29/2005 at 12:07:51 PM. Contact: ###-####. Stemwall on east end
|
BLD-Footing | 6/28/2005 | 6/28/2005 | 6/28/2005 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 6/28/2005 at 7:03:12 AM. Contact: ###-####.pwsi
|
BLD-Footing | 6/27/2005 | 6/27/2005 | 6/27/2005 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 6/27/2005 at 7:14:29 AM. Contact: ###-####.placed w/si
|
BLD-Footing | 6/22/2005 | 6/23/2005 | 6/23/2005 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 6/22/2005 at 4:28:42 PM. Contact: ###-####.wip/pwsi
|
BLD-Foundation | 6/21/2005 | 6/22/2005 | 6/22/2005 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 6/21/2005 at 3:58:15 PM. Contact: ###-####.pwsi
|
BLD-Foundation | 6/20/2005 | 6/21/2005 | 6/21/2005 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 6/20/2005 at 4:55:35 PM. Contact: ###-####.placed/w/si
|
BLD-Footing | 6/20/2005 | 6/21/2005 | 6/21/2005 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 6/20/2005 at 4:54:57 PM. Contact: ###-####. placed w/si
|
BLD-Foundation | 6/17/2005 | 6/20/2005 | 6/20/2005 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 6/17/2005 at 1:40:14 PM. Contact: ###-####.pending si
|
BLD-Footing | 6/17/2005 | 6/20/2005 | 6/20/2005 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 6/17/2005 at 1:38:27 PM. Contact: ###-####.si pending.
|
BLD-Footing | 6/15/2005 | 6/16/2005 | 6/16/2005 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 6/15/2005 at 3:28:09 PM. Contact: ###-####.placed w/si
|
BLD-Footing | 6/14/2005 | 6/15/2005 | 6/15/2005 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 6/14/2005 at 10:49:56 AM. Contact: ###-####. grid lines 1-11 to a-f rebar ok pending special insp.
|
BLD-Conference | 6/9/2005 | 6/9/2005 | 6/9/2005 | P | PASS |
Jim Storey
|
|
|
josh; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa need scope letter from mti
|