Permit Information
Permit NumberBLD05-00419
StatusFinaled
Name DEVCON CONSTRUCTION INC
Site Address 495 S CAPITOL BLVD
Project NameBODO BLDG # 8-Fndtn/Undergrnd
Customer Number 
ePlanReviewNo
Description
BoDo Building #8 (Foundation and Underground Phase) - To install the reinforced concrete footings and foundation for the new Hampton Inns Hotel. This foundation phase is being broken out from the shell and core phase, currently under review (BLD04-02876). This foundation permit is being released for construction prior to final approval of the shell and core phase. The applicant, by signing this permit, understands that he is proceeding at his own risk and that any foundation or underground modifications that are determined to be required during the review of the shell portion of this building project must be corrected. This is a footing, foundation and underground utility permit only and the applicant is not authorized to proceed beyond that point until the shell and core permit has been approved and issued. The ESC was approved under the shell permit, see attached copy of comments. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final2/9/20072/9/20072/9/2007PPASS
DetailsDave Hannah
DOC - Permit Finaled2/9/20072/9/20072/9/2007PPASS
DetailsDave Hannah
BLD-Framing/Rough-in8/3/20058/4/20058/4/2005APART
DetailsDave Hannah
ben; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa ok to cover ext walls 1st thru 4th floor on pert of north and south walls
BLD-Framing/Rough-in8/1/20058/2/20058/3/2005APART
DetailsDave Hannah
dennis; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa walked project wiyh george and framing contractor
BLD-Aging Inspection5/20/20055/20/20055/23/2005 PASS
DetailsDave Hannah
wip