BLD-Final | 2/21/2006 | 2/21/2006 | 2/21/2006 | P | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 2/21/2006 at 10:00:09 AM. Contact: ###-####.
|
BLD-Grading Inspection | 2/21/2006 | 2/21/2006 | 2/21/2006 | | DONE |
|
|
|
Grading completed according to the approved plans. Grading on the adjoining lots approved by those owners.
|
DOC - Permit Finaled | 2/21/2006 | 2/21/2006 | 2/21/2006 | P | PASS |
Tony Young
|
|
|
|
BLD-Final | 2/17/2006 | 2/17/2006 | 2/17/2006 | P | FAIL |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 2/17/2006 at 9:54:11 AM. Contact: ###-####. need trades still,, hill side
|
BLD-Grading Inspection | 2/17/2006 | 2/17/2006 | 2/17/2006 | | FAIL |
|
|
|
Rough grading is complete however fine grading and restoration of the adjoining lots must still be done.
|
BLD-Final | 2/16/2006 | 2/16/2006 | 2/16/2006 | P | NR |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 2/16/2006 at 8:14:57 AM. Contact: ###-####. need trades, hillside 1st
|
BLD-Wall cover | 9/2/2005 | 9/7/2005 | 9/7/2005 | P | DONE |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 9/2/2005 at 7:51:58 AM. Contact: ###-####. int shear
|
BLD-Wall cover | 9/2/2005 | 9/2/2005 | 9/2/2005 | P | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 9/2/2005 at 11:12:32 AM.
|
BLD-Energy code compliance | 8/26/2005 | 8/29/2005 | 8/29/2005 | A | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 8/26/2005 at 2:59:55 PM.
|
BLD-Framing/Rough-in | 8/24/2005 | 8/26/2005 | 8/26/2005 | P | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 8/24/2005 at 7:47:04 AM. Contact: ###-####. energy ok also,, will need int. shear inspection
|
BLD-Framing/Rough-in | 8/11/2005 | 8/11/2005 | 8/11/2005 | P | NR |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 8/11/2005 at 7:49:52 AM. Contact: ###-####. need reinspect on elec. 1st
|
BLD-Framing/Rough-in | 8/8/2005 | 8/10/2005 | 8/10/2005 | P | FAIL |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 8/8/2005 at 7:53:20 AM. Contact: ###-####. c/n posted,, also need re-inspection on electrical rough due to a lot of added/ modified electrical
|
BLD-Framing/Rough-in | 6/27/2005 | 6/28/2005 | 6/28/2005 | A | PART |
Tony Young
|
|
|
shear panel inspectin///justin; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa exterior shear ok
|
BLD-Framing/Rough-in | 6/27/2005 | 6/27/2005 | 6/27/2005 | P | NR |
Tony Young
|
|
|
mike Note: shear panel; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles no plans on site,, no inspection made
|
BLD-Foundation | 5/25/2005 | 5/25/2005 | 5/25/2005 | P | PART |
Tony Young
|
|
|
jack; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Foundation | 5/23/2005 | 5/24/2005 | 5/24/2005 | P | NR |
Tony Young
|
|
|
foundation wall inspection///jack; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
BLD-Footing | 5/19/2005 | 5/20/2005 | 5/20/2005 | A | PART |
Tony Young
|
|
|
jack; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|