Permit Information
Permit NumberBLD05-00994
StatusFinaled
Name TURN-KEY INC
Site Address 3201 W AIRPORT WAY
Project NameAIRPORT
Customer Number 
ePlanReviewNo
Description
(BAGGAGE CONVEYOR SYSTEM - BOISE AIR TERMINAL) This building is fully fire sprinklered for fire area reasons. To install a new baggage conveyor system to serve the existing Delta Airlines counter located in the ticket lobby of the Boise City Air Terminal. Baggage will be conveyed from the ticket lobby located on the 2nd story to the existing make-up baggage (out-going) area located on the 1st story. A 5.0 foot by 17.25 foot opening will be cut in the existing 2nd story concrete floor. Work is to include new steel beams, knife plates welded to steel beams, modifications to existing steel beams, steel bolts, a 2-hr fire-resistance rated "dog house" constructed over the new floor opening, a 90 minute rated coiling door assembly, a 60 minute rated coiling door assembly, interior nonbearing walls, reconfigured suspended ceiling, millwork, and finishes. All work shall comply with the approved drawings and all applicable codes. Alterations to the fire sprinkler system shall comply with NFPA 13 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection3/12/20073/12/20073/13/2007PPASS
DetailsForrest France
Fire life safety okay for final.
DOC - Permit Finaled3/12/20073/12/20073/12/2007PPASS
DetailsJim Storey
BLD-Aging Inspection3/8/20073/8/20073/12/2007 FAIL
DetailsJim Storey
pending fire responce .
BLD-Aging Inspection1/3/20071/3/20071/3/2007 FAIL
DetailsJim Storey
ncfi
BLD-Aging Inspection10/30/200610/30/200610/30/2006 FAIL
DetailsJim Storey
pending actions from fire.
BLD-Aging Inspection8/28/20068/28/20068/28/2006 NR
DetailsJim Storey
pending fire.
BLD-Aging Inspection6/26/20066/26/20066/26/2006 FAIL
DetailsJim Storey
pending fire per note .
BLD-Aging Inspection4/24/20064/24/20064/24/2006 FAIL
DetailsJim Storey
pending fire.
BLD-Aging Inspection2/20/20062/20/20062/21/2006 DEFR
DetailsJim Storey
to fire
BLD-Aging Inspection12/20/200512/20/200512/23/2005PDONE
DetailsForrest France
Left message with Martin Hale at ###-#### regarding the need to schedule an inspection for the related fire sprinkler permits and life safety inspection for this project which has not been requested by the general contractor to date.
BLD-Aging Inspection12/20/200512/20/200512/20/2005 DEFR
DetailsJim Storey
to fire
BLD-Aging Inspection10/19/200510/19/200510/19/2005 NR
DetailsJim Storey
pending fire.
BLD-Aging Inspection8/19/20058/19/20058/19/2005 PASS
DetailsJim Storey
wip
BLD-Framing/Rough-in6/3/20056/6/20056/6/2005APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 6/3/2005 at 8:39:37 AM. Contact: ###-####. framing ok /special insp pending all reports for welding and fireproofing.