BLD-Final | 6/15/2006 | 6/16/2006 | 6/16/2006 | A | DONE |
Mike Jordan
|
|
|
Jim Snyder, final reinspect, late a.m. please Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt. All issues have been resolved. ok for perm occ.
|
Permanent Occupancy | | 6/16/2006 | 6/16/2006 | | DONE |
|
|
|
|
BLD-Aging Inspection | 5/9/2006 | 5/9/2006 | 5/9/2006 | | PASS |
Mike Jordan
|
|
|
Work is in progress. Noted that racking permit has been issued and are being installed.
|
BLD-Final | 11/4/2005 | 11/7/2005 | 11/7/2005 | A | PART |
Mike Jordan
|
|
|
don ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie. Temp occ granted. Needs racking permit. Also needs to remove exit sign in warehouse or provide the proper lighting. ( This is not the required exit) provide special insp. letter. Provide self closures on restroom doors or post sign on wall.
|
FIRE-Final Inspection | 11/4/2005 | 11/7/2005 | 11/7/2005 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given with Dave Hanniman's permission until the racking permit has been submitted, inspected and finaled. Life safety items are passed.
|
BLD-Final | 11/2/2005 | 11/2/2005 | 11/2/2005 | P | CANC |
Tom Arcoraci
|
|
|
|
BLD-Final | 11/1/2005 | 11/2/2005 | 11/2/2005 | A | CANC |
Tom Arcoraci
|
|
|
don; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
FIRE-Final Inspection | 11/1/2005 | 11/1/2005 | 11/1/2005 | P | FAIL |
Troy Cobbley
|
|
|
Repair and test all emergency lights and exit signs, provide racking permit, provide signage for fire dept access, provide the additional fire extinguisher as discussed on the east showroom wall.
|
BLD-Final | 10/25/2005 | 10/27/2005 | 10/27/2005 | P | NR |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 10/25/2005 at 2:46:29 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 10/6/2005 | 10/7/2005 | 10/7/2005 | P | PASS |
Mike Jordan
|
|
|
grid ceiling insp//pete; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
BLD-Framing/Rough-in | 9/30/2005 | 10/3/2005 | 10/3/2005 | A | PART |
Mike Jordan
|
|
|
ceiling grid inspection please////pete; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
BLD-Framing/Rough-in | 9/13/2005 | 9/14/2005 | 9/14/2005 | P | PART |
Tom Arcoraci
|
|
|
pete; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa walls ok after elec approval
|
BLD-Framing/Rough-in | 9/8/2005 | 9/8/2005 | 9/8/2005 | P | PART |
Tom Arcoraci
|
|
|
pete; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles eng ok with strap nailing
|
BLD-Framing/Rough-in | 9/6/2005 | 9/7/2005 | 9/7/2005 | P | PASS |
Dave Hannah
|
|
|
pete ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie roof nailing ok but still needs to nail allroof straping
|
BLD-Footing | 7/14/2005 | 7/14/2005 | 7/14/2005 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 7/14/2005 at 8:57:41 AM.
|