BLD-Final | 5/11/2006 | 5/15/2006 | 5/15/2006 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 5/11/2006 at 8:54:51 AM. Contact: ###-####. ok for perm occ
|
Permanent Occupancy | | 5/15/2006 | 5/15/2006 | | DONE |
|
|
|
|
FIRE-Final Inspection | 5/9/2006 | 5/10/2006 | 5/10/2006 | A | PASS |
Forrest France
|
|
|
Fire life safety is satisfactory, inspection passed.
|
BLD-Final | 5/3/2006 | 5/4/2006 | 5/4/2006 | A | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 5/3/2006 at 10:20:20 AM. Contact: ###-####.needs fire sign offs
|
BLD-Foundation | 11/14/2005 | 11/15/2005 | 11/15/2005 | A | CANC |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 11/14/2005 at 9:44:02 AM. Contact: ###-####. Called wrong insp in.
|
BLD-Footing | 11/14/2005 | 11/14/2005 | 11/14/2005 | P | CANC |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 11/14/2005 at 9:43:18 AM. Contact: ###-####.
|
BLD-Wall cover | 10/24/2005 | 10/25/2005 | 10/25/2005 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 10/24/2005 at 1:37:09 PM. Contact: ###-####. ok to move into phase one area so phase two can start demo
|
BLD-Framing/Rough-in | 10/12/2005 | 10/13/2005 | 10/13/2005 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 10/11/2005 at 7:20:56 AM. Contact: ###-####.ceiling grid grid ok
|
BLD-Framing/Rough-in | 10/12/2005 | 10/12/2005 | 10/13/2005 | P | DEFR |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 10/11/2005 at 7:20:56 AM. Contact: ###-####.ceiling grid out of time rescheduled
|
BLD-Wall cover | 10/11/2005 | 10/12/2005 | 10/13/2005 | A | CANC |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 10/11/2005 at 7:20:56 AM. Contact: ###-####. out of time rescheduled
|
BLD-Wall cover | 8/24/2005 | 8/25/2005 | 8/25/2005 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 8/24/2005 at 7:05:38 AM. Contact: ###-####.ok to cover infill walls still needs to finish corr walls
|