BLD-Final | 12/23/2005 | 12/23/2005 | 12/23/2005 | P | PASS |
Forrest France
|
|
|
c/n items are complete, okay for final
|
BLD-Final | 12/12/2005 | 12/13/2005 | 12/13/2005 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 12/12/2005 at 2:47:42 PM. Contact: ###-####. ok for temp occ ok for perm after plb gos perm
|
FIRE-Final Inspection | 12/9/2005 | 12/12/2005 | 12/12/2005 | P | PASS |
Forrest France
|
|
|
Fire life safety issues are acceptable, corrections have been completed, inspection passed.
|
Permanent Occupancy | | 12/12/2005 | 12/12/2005 | | DONE |
|
|
|
|
BLD-Wall cover | 11/30/2005 | 11/30/2005 | 11/30/2005 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 11/30/2005 at 9:34:50 AM. Contact: ###-####. cieling grid ok
|
BLD-Framing/Rough-in | 10/28/2005 | 10/28/2005 | 10/31/2005 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 10/28/2005 at 7:12:42 AM. Contact: ###-####. ok to cover after elec r/i
|
BLD-Framing/Rough-in | 10/19/2005 | 10/19/2005 | 10/20/2005 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 10/19/2005 at 8:33:35 AM. Contact: ###-####. ok to one side walls
|