BLD-Final | 9/1/2006 | 9/5/2006 | 9/5/2006 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 9/1/2006 at 12:50:03 PM. Contact: (208) 863-291 Shell and core ok. cert of comp. was issued.
|
DOC - Permit Finaled | 9/5/2006 | 9/5/2006 | 9/5/2006 | P | PASS |
Mike Jordan
|
|
|
Shell and core final ok. Code enforcement sighned temp only due to missig bark. Did note that bark has been installed and noted to contractor to call code enforcement for final insp.
|
FIRE-Final Inspection | 8/30/2006 | 8/30/2006 | 8/30/2006 | P | PASS |
Troy Cobbley
|
|
|
Life safety finaled
|
Code Occupancy Approval Temp | 8/25/2006 | 8/25/2006 | 8/28/2006 | P | FAIL |
Scott M.Brown
|
|
|
I ONLY SIGNED TEMP OCCUPANCY DUE TO MISSING BARK ON WEST SIDE.
|
FIRE-Final Inspection | 8/24/2006 | 8/25/2006 | 8/25/2006 | A | FAIL |
Troy Cobbley
|
|
|
Provide address and repair the west side emergency discharge light.
|
BLD-Framing/Rough-in | 8/23/2006 | 8/23/2006 | 8/23/2006 | P | CANC |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/23/2006 at 9:14:15 AM.
|
BLD-Energy code compliance | 8/23/2006 | 8/23/2006 | 8/23/2006 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/23/2006 at 9:14:15 AM.
|
BLD-Aging Inspection | 8/9/2006 | 8/9/2006 | 8/9/2006 | | PASS |
Mike Jordan
|
|
|
wip
|
BLD-Framing/Rough-in | 6/5/2006 | 6/5/2006 | 6/5/2006 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 6/5/2006 at 9:49:49 AM. Contact: ###-####. Reveiwed submitted UL specs for listed penetrations and inspected penetrations at masonry wall and at mdf walls.
|
BLD-Framing/Rough-in | 5/11/2006 | 5/12/2006 | 5/12/2006 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 5/11/2006 at 2:59:00 PM. Contact: ###-####. shear nailing on exterior of bldg. ok to cover. Needs to get data for elec. penetrations in 1hr rated wood panels.
|
BLD-Framing/Rough-in | 4/25/2006 | 4/25/2006 | 4/25/2006 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 4/25/2006 at 7:36:14 AM. Contact: ###-####. OK to install soffit material.
|
BLD-Framing/Rough-in | 4/11/2006 | 4/12/2006 | 4/12/2006 | A | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 4/11/2006 at 9:59:16 AM. Contact: ###-####. Inspected shear nailing on south wall, roof sheating and all related hardware, holdowns and roof trusses. Noted all strapping on bldg. walls is complete. wip on straps from lvl's to bldg. Also noted wip on the two hour firewall extension from cmu wall out to canopy down to the soffit. Noted letter from engineer approving the use of fire rated plywood on exterior of bldg. in leiu of the two layers of 5/8 type X at either side of masonry wall.
|
BLD-Foundation | 3/15/2006 | 3/15/2006 | 3/15/2006 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 3/15/2006 at 11:02:16 AM. Contact: ###-####. Exterior column pad pedestals, west side of building.
|
BLD-Footing | 3/14/2006 | 3/14/2006 | 3/14/2006 | P | PASS |
Jim Storey
|
|
|
harvey; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa east pad ft ok.
|
BLD-Foundation | 2/13/2006 | 2/14/2006 | 2/14/2006 | A | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 2/13/2006 at 3:01:38 PM. Contact: ###-####. Noted some clearance issues. Special insp. to verify repair.
|
BLD-Footing | 2/8/2006 | 2/9/2006 | 2/9/2006 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 2/8/2006 at 12:29:15 PM. Contact: ###-####. perimeter footings and footing for masonry seperation wall.
|