Permit Information
Permit NumberBLD05-02222
StatusFinaled
Name DEVCON CONSTRUCTION INC
Site Address 722 W BROAD ST
Project NameOFFICE DEPOT BODO 7
Customer Number 
ePlanReviewNo
Description
(OFFICE DEPOT - BODO BLDG #7 - 1ST FLR - SOUTHEAST CORNER) This building is fire sprinklered for fire area and to allow the multitheater complex. To create a 19,293 square foot retail sales tenant space located on the 1st story of an existing 138,293 square foot, 3 story building (BODO Building #7). Work is to include 2 restrooms accessible to the disabled, an entry vestibule, interior nonbearing walls, suspended ceilings, and finishes. The racking will be installed under a separate permit. The work shall comply with the approved drawings, the plan review report, and all applicable codes. The fire sprinkler system shall comply with NFPA 13 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final4/4/20064/5/20064/5/2006PPASS
DetailsDave Hannah
paul fishley; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa ok for perm occ
FIRE-Final Inspection4/4/20064/5/20064/5/2006APASS
DetailsTroy Cobbley
Life safety finaled, related sprinkler and alarm permits are finaled.
Permanent Occupancy 4/5/20064/5/2006 DONE
Details
BLD-Other2/9/20062/9/20062/9/2006 DONE
Temp. Occ. Cert. #5316 extended for 90 days per Jenifer until 5-22-06.
BLD-Final11/25/200511/25/200511/28/2005PPART
DetailsDave Hannah
ok for temp occ ok for perm ater all others go perm
FIRE-Final Inspection11/21/200511/21/200511/21/2005PPART
DetailsForrest France
Life safety is acceptable, final pending shell permits final approval, currently on a temp.
FIRE-Final Inspection11/18/200511/18/200511/18/2005PFAIL
DetailsForrest France
Missing one required exit sign, one emergency light at the back restroom is not functional, provide exit discharge lighting, exit sign at the main exit does not illuminate on backup power, provide an additional link on opposite side of the roll up door, provide signage at the roll up door, need permanent address numbers, provide curb painting as discussed, main vestibule is not finished at this time.
BLD-Final11/18/200511/18/200511/18/2005PFAIL
DetailsJim Storey
Internet Inspection Request from: Alex Monge fire stopping/ door trip test/ signage door hardware maine entry.
FIRE-Final Inspection11/16/200511/17/200511/17/2005AFAIL
DetailsForrest France
Not ready for final per Dennis the GC, need fire extinguishers installed, missing one exit sign, signage at doors, test emergency lights, no inspection performed.
BLD-Final11/16/200511/17/200511/17/2005ANR
DetailsJim Storey
Internet Inspection Request from: Alex Monge Not ready. Check internet to determine which finals from other trades are still outstanding. Cannot final without other trade sign offs.