Permit Information
Permit NumberBLD05-02631
StatusFinaled
Name ESI
Site Address 3669 S TK AVE
Project NameSFPII Building 2
Customer Number 
ePlanReviewNo
Description
(VANILLA FINISH-NO TENANT)(SFP II-BLDG 2) To construct a 4,895 sq.ft. vanilla finish space for future warehouse with 2 offices and 1 accessible restroom. No occupany allowed under this permit. Work to include, construction of interior partitions to create offce area and restroom, installation of a suspended ceiling system in office area, installation of a two zone HVAC system that will condition both the warehouse and office areas, installation of lighting and related electrical outlets, miscelaneous related interior finishes, This building is fully fire sprinklered any alterations to the sprinkler system shall be per NFPA #13 as regulated by the fire department. Any storage racking over eight feet high will require a separate permit. (rmh) The shell of this building is currently under construction permitted under Bld04-00467.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final4/10/20064/11/20064/11/2006PPASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 4/10/2006 at 2:36:13 PM. Contact: ###-####. v-shell l/c isued.
DOC - Permit Finaled4/11/20064/11/20064/11/2006PPASS
DetailsJim Storey
v shell l/c isued
FIRE-Final Inspection4/10/20064/11/20064/11/2006APASS
DetailsForrest France
Life safety inspection satisfactory for vanilla finish, contractor to install visual lock indicator at the main entry/exit today as discussed.
BLD-Framing/Rough-in3/10/20063/13/20063/13/2006APART
DetailsJim Storey
Brian; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong framing ok pending others.
BLD-Aging Inspection2/7/20062/7/20062/7/2006 NR
DetailsJim Storey
ncfi