BLD-Final | 11/16/2007 | 11/16/2007 | 11/16/2007 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/16/2007 at 9:48:30 AM.
|
Code Occupancy Approval | 11/15/2007 | 11/15/2007 | 11/15/2007 | P | PASS |
Dena Gambrel
|
|
|
|
Code Occupancy Approval | 10/25/2007 | 10/25/2007 | 10/25/2007 | P | FAIL |
Dena Gambrel
|
|
|
10-24-07 Most of landscape is in. There is an area on the west side of the building that needs to be finished. Gail will either finish it or obtain a bid for the remaining landscape.
|
BLD-Aging Inspection | 9/21/2007 | 9/21/2007 | 9/21/2007 | | DONE |
Tom Arcoraci
|
|
|
on temp
|
BLD-Aging Inspection | 7/20/2007 | 7/20/2007 | 7/23/2007 | | DONE |
Tom Arcoraci
|
|
|
on temp
|
BLD-Final | 4/20/2007 | 4/23/2007 | 4/23/2007 | P | PART |
Jim Sly
|
|
|
dale; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles OK for Temp Occ.
|
BLD-Final | 4/19/2007 | 4/20/2007 | 4/20/2007 | P | FAIL |
Jim Storey
|
|
|
Gale; Phone #: ###-#### Internet Inspection Request from: Stacie Backus fire potect under stairs and walls supporting stair/ smoke seals/wire glazing/landing exterior exit/sink protection 2nd floor
|
Code Occupancy Approval Temp | 4/19/2007 | 4/19/2007 | 4/19/2007 | P | FAIL |
Dena Gambrel
|
|
|
4-19-07 Need to Bond for landscape, curbing, striping and paving for the amount of $29,849.00. Correction notice issued.
|
BLD-Final | 4/17/2007 | 4/18/2007 | 4/18/2007 | A | NR |
Tom Arcoraci
|
|
|
gale; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
|
FIRE-Final Inspection | 4/5/2007 | 4/6/2007 | 4/6/2007 | A | PASS |
Forrest France
|
|
|
Necessary corrections have been verified, final fire life safety inspection passed.
|
BLD-Other | 3/6/2007 | 3/7/2007 | 3/7/2007 | A | PASS |
Tom Arcoraci
|
|
|
gayle - grid ceiling; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
BLD-Framing/Rough-in | 12/28/2006 | 12/29/2006 | 12/29/2006 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 12/28/2006 at 3:29:02 PM. Contact: ###-####. insulation also ok
|
BLD-Other | 11/17/2006 | 11/17/2006 | 11/17/2006 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/17/2006 at 8:30:12 AM. Contact: ###-####. ok to roof
|
BLD-Other | 10/11/2006 | 10/12/2006 | 10/12/2006 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 10/11/2006 at 11:36:03 AM. Contact: ###-####. pending spec insp
|
BLD-Aging Inspection | 9/4/2006 | 9/4/2006 | 9/5/2006 | | PASS |
Tom Arcoraci
|
|
|
|
BLD-Foundation | 7/3/2006 | 7/5/2006 | 7/5/2006 | A | PART |
Tom Arcoraci
|
|
|
micyale; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley spec insp on site
|
BLD-Foundation | 6/30/2006 | 6/30/2006 | 6/30/2006 | P | NR |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 6/30/2006 at 9:24:36 AM. Contact: ###-####.
|
BLD-Footing | 6/28/2006 | 6/29/2006 | 6/29/2006 | A | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 6/28/2006 at 5:13:12 PM. Contact: ###-####. perimeter footings. special insp. not required for conc. testing.
|
BLD-Aging Inspection | 6/19/2006 | 6/19/2006 | 6/23/2006 | | PASS |
Tom Arcoraci
|
|
|
|