Permit Information
Permit NumberBLD05-02662
StatusFinaled
Name COLE + POE ARCHITECTS
Site Address 519 W FRONT ST
Project NameFRONT 5 BUILDING
Customer Number 
ePlanReviewNo
Description
(COLE + POE ARCHITECTS - EXPANSION)(FRONT 5 BLDG) New 870 sq. ft. expansion to an existing 3,315 sq. ft. office tenant per approved plans. The existing 2,555 sq. ft. first floor area will have a 110 sq. ft. expansion for a new first floor total of 2,665 sq. ft. The existing 760 sq. ft. second floor will have a 760 sq. ft. expansion for a new second floor total of 1,520 sq. ft. The new total for the entire tenant space will be 4,185 sq. ft. Work to include new interior walls, new interior doors and windows, a complete new interior storefront window wall at the edge of the second floor, interior finish, a new sink and some casework, plumbing work, and some electrical work. A new Certificate of Occupancy is to be issued when completed and approved. NOTE: This building is fully fire sprinklered. JCB
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final1/5/20061/6/20061/6/2006PPASS
DetailsDave Hannah
dave pending fire fn ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie ok for perm occ
FIRE-Final Inspection1/5/20061/6/20061/6/2006PPASS
DetailsForrest France
Items on c/n are complete, fire life safety passed inspection.
BLD-Final1/4/20061/5/20061/5/2006PNR
DetailsDave Hannah
dave; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
FIRE-Final Inspection1/4/20061/5/20061/5/2006AFAIL
DetailsForrest France
Need to provide one fire ext. as required, all remaining life safety issues are acceptable.
BLD-Framing/Rough-in11/23/200511/23/200511/25/2005PPASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 11/23/2005 at 8:28:36 AM. Contact: ###-####. ok to cover after elec r/i