BLD-Final | 8/22/2006 | 8/23/2006 | 8/23/2006 | A | PASS |
Jim Storey
|
|
|
gregg; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
|
DOC - Permit Finaled | 8/23/2006 | 8/23/2006 | 8/23/2006 | P | PASS |
Jim Storey
|
|
|
|
BLD-Final | 8/17/2006 | 8/18/2006 | 8/18/2006 | A | FAIL |
Jim Storey
|
|
|
Greg; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt need pw/ hand rail to low 2nd stair from east end of bldg.
|
FIRE-Final Inspection | 8/17/2006 | 8/18/2006 | 8/18/2006 | A | PASS |
Forrest France
|
|
|
c/n item is complete, inspection passed.
|
Code Occupancy Approval | 8/17/2006 | 8/17/2006 | 8/17/2006 | P | PASS |
Wm. Michael Meloy
|
|
|
Inspection at 15:10 found compliance met.
|
FIRE-Final Inspection | 8/10/2006 | 8/11/2006 | 8/11/2006 | A | FAIL |
Forrest France
|
|
|
Need to provide signs or markings prohibiting parking for the fire dept. looped access road per review comments note #5.
|
BLD-Framing/Rough-in | 7/5/2006 | 7/5/2006 | 7/5/2006 | P | PASS |
Jim Storey
|
|
|
gregg; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley riser rm ok
|
BLD-Foundation | 6/16/2006 | 6/16/2006 | 6/16/2006 | P | PART |
Jim Storey
|
|
|
gregg; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley si ok on welding qustion as to diaphram snow drift area/ one pannel joist conection. floor pour back ok
|
BLD-Foundation | 5/8/2006 | 5/9/2006 | 5/9/2006 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 5/8/2006 at 4:33:05 PM. Contact: ###-####.pannels placed with si approval.
|
BLD-Footing | 5/5/2006 | 5/8/2006 | 5/8/2006 | A | PASS |
Jim Storey
|
|
|
aprox 900 am 301 si south ft ok
|
BLD-Footing | 5/5/2006 | 5/5/2006 | 5/5/2006 | P | PART |
Jim Storey
|
|
|
Phone #: ###-#### Internet Inspection Request from: Cathy Chiles wip.
|