Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD06-00212
StatusFinaled
Name DAVE EVANS CONSTRUCTION
Site Address 7960 W RIFLEMAN ST
Project NameTowne Square Station Bldg B
Customer Number 
ePlanReviewNo
Description
RCE-2452 per Travis (Dave Evans Construction) 3-10-06 eus/// Town Square Station Building "B" (Retail Shell) - To build a new 19,285 square foot, two story retail and office shell building and related site improvements. This building is constructed of masonry and wood framed exterior walls and wood framed interior walls, floors and roof system. This is a shell building only. No occupancy is allowed under this permit. Separate tenant improvement permits will be required to finish this building for occupancy. All construction per the approved plans. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final4/10/20074/10/20074/10/2007PPASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 4/10/2007 at 11:07:27 AM. Contact: ###-####.
DOC - Permit Finaled4/10/20074/10/20074/10/2007PPASS
DetailsMike Jordan
Letter of compliance issued.
BLD-Final4/6/20074/6/20074/6/2007PCANC
DetailsMike Jordan
Scheduled by a contractor via Hello! on 4/6/2007 at 11:28:56 AM. Contact: ###-####.
Code Occupancy Approval4/6/20074/6/20074/6/2007PPASS
DetailsScott M.Brown
FINAL SIGNED OFF
Code Occupancy Approval3/7/20073/7/20073/9/2007PCANC
DetailsScott M.Brown
FIRE-Final Inspection3/8/20073/8/20073/8/2007APASS
DetailsTroy Cobbley
Life safety passed
BLD-Final3/8/20073/8/20073/8/2007APART
DetailsMike Jordan
Scheduled by a contractor via Hello! on 3/8/2007 at 6:51:52 AM. Contact: ###-####. ok temp occ.
BLD-Final3/7/20073/7/20073/7/2007PNR
DetailsMike Jordan
Code Occupancy Approval3/7/20073/7/20073/7/2007PPASS
DetailsScott M.Brown
TEMP ONLY TRASH INCL AND A FEW ROCKS NOT COMPLETE
BLD-Final3/7/20073/7/20073/7/2007ANR
DetailsMike Jordan
Scheduled by a contractor via Hello! on 3/7/2007 at 7:28:37 AM. Contact: ###-####. Still needs other trades.
FIRE-Final Inspection3/7/20073/7/20073/7/2007ACANC
DetailsAlan Hauser
Scheduled by a contractor via Hello! on 3/7/2007 at 7:18:14 AM. Contact: ###-####.
FIRE-Final Inspection3/5/20073/5/20073/5/2007PCANC
DetailsTroy Cobbley
Fire alarm is not ready yet. No inspection was performed.
FIRE-Final Inspection3/1/20073/1/20073/2/2007PFAIL
DetailsTroy Cobbley
Need fire alarm and fire sprinkler signed off first. No inspection performed.
FIRE-Final Inspection3/1/20073/2/20073/2/2007AFAIL
DetailsTroy Cobbley
Need to get the sprinkler permit and fire alarm permits finaled first. No inspection performed.
BLD-Framing/Rough-in12/5/200612/5/200612/5/2006PPASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 12/5/2006 at 10:09:12 AM. Contact: ###-####.
BLD-Framing/Rough-in10/2/200610/3/200610/3/2006APART
DetailsMike Jordan
All straps have been installed. Will complete remaing of framing insp. once ri are done.
BLD-Framing/Rough-in10/2/200610/2/200610/2/2006PCANC
DetailsMike Jordan
Scheduled by a contractor via Hello! on 10/2/2006 at 7:56:41 AM. Contact: ###-####. rescheduled for tomorrow by cont.
BLD-Framing/Rough-in9/28/20069/28/20069/28/2006PPART
DetailsMike Jordan
Scheduled by a contractor via Hello! on 9/28/2006 at 7:55:59 AM. Contact: ###-####. Shear nailing at roofs walls and second floor. Still needs ti instal LTT straps from masonry wall to roof sheating, Straps to tie in masonry walls to framed walls and needs additional MSTC 12 strap and overlap an min. 4ft. to complete tie in. All blocking was installed and diaphragm nailing was ok. Second floor framing ok for gypcrete.
BLD-Framing/Rough-in8/30/20068/30/20068/30/2006PPART
DetailsMike Jordan
Scheduled by a contractor via Hello! on 8/30/2006 at 9:16:13 AM. Contact: ###-####. Shearwall insp. south walls at east and west storefronts.
BLD-Concrete7/19/20067/20/20067/20/2006APART
DetailsMike Jordan
Scheduled by a contractor via Hello! on 7/19/2006 at 9:22:21 AM. Contact: ###-####. work complete. did review special insp. reports. ok
BLD-Foundation7/19/20067/20/20067/20/2006APART
DetailsMike Jordan
Scheduled by a contractor via Hello! on 7/19/2006 at 9:21:54 AM. Contact: ###-####. work complete. did review special insp reports. ok.
BLD-Footing7/19/20067/20/20067/20/2006APART
DetailsMike Jordan
Scheduled by a contractor via Hello! on 7/19/2006 at 9:21:24 AM. Contact: ###-####. work complete. But reviewed special insp reports. ok.
BLD-Aging Inspection6/12/20066/12/20066/13/2006 DONE
DetailsMike Jordan
Called permit holder ( Dave Evans Const.) They noted that they are no longer doing the job, and that Steed const is doing the job.