Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberBLD06-00322
StatusFinaled
Name THE CHRISTENSEN CORPORATION
Site Address 950 W BANNOCK ST Unit: 620
Project Name10TH & BANNOCK-6TH FLR
Customer Number 
ePlanReviewNo
Description
(RCE #8247 - CHRISTENSEN CORP (THE CHRISTENSEN CORPORATION - BANNER BANK BLDG - STE 620) This building is fire sprinklered because it is a high-rise. To construct a 2,296 square foot office tenant space on the 6th story of a high-rise building. Work is to include interior Nordwall demountable nonbearing partitions, doors, and sidelights. The access floor system and the suspended ceilings were installed under permit BLD05-02939. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes. The fire sprinkler system shall comply with NFPA 13 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final4/25/20074/25/20074/25/2007PPASS
DetailsDave Hannah
Steve; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt ok for perm occ
Permanent Occupancy 4/25/20074/25/2007 DONE
Details
BLD-Final5/31/20066/1/20066/1/2006PPART
DetailsTony Young
greg; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
temp ok
FIRE-Final Inspection5/31/20066/1/20066/1/2006APASS
DetailsForrest France
Items on correction notice have been completed, fire life safety inspection passed.
BLD-Final5/30/20065/30/20065/31/2006PNR
DetailsDave Hannah
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung needs fire life saftey final
FIRE-Final Inspection5/30/20065/30/20065/30/2006PFAIL
DetailsTroy Cobbley
Final sprinkler permit and provide permanant emergency lighting and the additional exit signs in corridor.
BLD-Final5/26/20065/30/20065/30/2006PCANC
DetailsDave Hannah
greg - ; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Inspection cancelled from web by: Rita DeYoung
BLD-Final5/25/20065/26/20065/26/2006PNR
DetailsDave Hannah
greg; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
FIRE-Final Inspection5/25/20065/26/20065/26/2006AFAIL
DetailsForrest France
The project related fire sprinkler permit must be requested for final inspection and approval prior to BLD life safety final, missing door hardware at the glass doors, confrence room doors are not installed yet, temporary emergency lights are installed at this time. Informed contractor that only a "partial" could be given if permanent lighting was not in place including emergency lights.
FIRE-Alarm Testing5/25/20065/26/20065/26/2006ADEFR
DetailsForrest France
Duplicate inspection request already called in.
BLD-Framing/Rough-in5/25/20065/25/20065/25/2006PPASS
DetailsDave Hannah
greg; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles ok to cover walls
BLD-Framing/Rough-in5/24/20065/25/20065/25/2006ADEFR
DetailsDave Hannah
greg; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
BLD-Framing/Rough-in5/22/20065/23/20065/24/2006PPART
DetailsDave Hannah
greg; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie ok to cover both sides of walls