BLD-Final | 5/11/2007 | 5/11/2007 | 5/11/2007 | P | PASS |
Mike Jordan
|
|
|
mel ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith. Window replaced. ok for perm occ.
|
Code Occupancy Approval | 5/11/2007 | 5/11/2007 | 5/11/2007 | P | PASS |
Scott M.Brown
|
|
|
OK FOR FINAL AND BOND RELEASE
|
Permanent Occupancy | | 5/11/2007 | 5/11/2007 | | DONE |
|
|
|
|
BLD-Final | 4/16/2007 | 4/16/2007 | 4/16/2007 | P | PART |
Mike Jordan
|
|
|
mel ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith. Ok for temp occ. Needs to install tempered glass at win dow in assembly room.
|
Code Occupancy Approval Temp | 4/16/2007 | 4/16/2007 | 4/16/2007 | P | DONE |
Scott M.Brown
|
|
|
PRESSURE LAND SCAPE SYSTEM NOT COMPLETED AND HYDROSEEDING, NEED TO BOND FOR $4,230
|
BLD-Final | 4/13/2007 | 4/13/2007 | 4/13/2007 | P | NR |
Mike Jordan
|
|
|
mel ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
BLD-Final | 4/12/2007 | 4/13/2007 | 4/13/2007 | A | NR |
Mike Jordan
|
|
|
Mel; Phone #: ###-#### Internet Inspection Request from: Stacie Backus. Needs code enforcement for final.
|
FIRE-Final Inspection | 4/5/2007 | 4/6/2007 | 4/6/2007 | A | PASS |
Forrest France
|
|
|
Fire life safety final inspection passed.
|
FIRE-Final Inspection | 3/28/2007 | 3/28/2007 | 3/28/2007 | P | NR |
Forrest France
|
|
|
Need project related fire alarm and sprinkler permit finals prior to BLD life safety inspection.
|
BLD-Other | 3/20/2007 | 3/20/2007 | 3/20/2007 | P | PASS |
Mike Jordan
|
|
|
Mel Ceiling Grid; Phone #: ###-#### Internet Inspection Request from: Stacie Backus. Ceiling grid ok.
|
BLD-Other | 3/14/2007 | 3/14/2007 | 3/14/2007 | P | FAIL |
Mike Jordan
|
|
|
mel - ceiling grid ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith. Installation not complete. Wires needed for fixtures and approved clips need to be used.
|
BLD-Other | 3/9/2007 | 3/9/2007 | 3/9/2007 | P | PASS |
Mike Jordan
|
|
|
Mel Seismic; Phone #: ###-#### Internet Inspection Request from: Stacie Backus
|
BLD-Framing/Rough-in | 2/8/2007 | 2/8/2007 | 2/8/2007 | P | PASS |
Mike Jordan
|
|
|
mel; Phone #: ###-#### Internet Inspection Request from: Victoria Beall. Roof framing at truck bays.
|
BLD-Energy code compliance | 1/29/2007 | 1/30/2007 | 1/30/2007 | A | PASS |
Mike Jordan
|
|
|
mel; Phone #: ###-#### Internet Inspection Request from: Victoria Beall. 1st. floor ok to cover.
|
BLD-Energy code compliance | 1/26/2007 | 1/26/2007 | 1/29/2007 | P | PART |
Mike Jordan
|
|
|
nell; Phone #: ###-#### Internet Inspection Request from: Barbara Stitt. ok to one side.
|
BLD-Framing/Rough-in | 1/25/2007 | 1/25/2007 | 1/25/2007 | P | PART |
Mike Jordan
|
|
|
mel; Phone #: ###-#### Internet Inspection Request from: Victoria Beall. Needs to fire block all furouts. Add addtional studs under 2ply ML at statirway, either side. Ok to insul.
|
BLD-Energy code compliance | 1/22/2007 | 1/23/2007 | 1/23/2007 | P | PART |
Mike Jordan
|
|
|
mel; Phone #: ###-#### Internet Inspection Request from: Darla Downs2nd floor only. All fireblocking complete.
|
BLD-Framing/Rough-in | 1/10/2007 | 1/11/2007 | 1/11/2007 | A | PART |
Mike Jordan
|
|
|
mel; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. Upper roof framing and 2nd floor interior and perimeter walls. Needs to fireblock at ceiling line all mech chases and concealed spaces.
|
BLD-Other | 12/5/2006 | 12/6/2006 | 12/6/2006 | P | PASS |
Mike Jordan
|
|
|
mel Note: roof sheeting; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. Shear nailing for reamainder of roof.
|
BLD-Other | 11/29/2006 | 11/30/2006 | 11/30/2006 | A | PART |
Mike Jordan
|
|
|
mel Note: shear roof; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. Shear nailing at lower roof section.
|
BLD-Framing/Rough-in | 11/16/2006 | 11/17/2006 | 11/17/2006 | A | PART |
Mike Jordan
|
|
|
mel ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith. Exterior shearwall nailing.
|
BLD-Framing/Rough-in | 11/1/2006 | 11/3/2006 | 11/3/2006 | A | DEFR |
Mike Jordan
|
|
|
rebar --harvey ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD-Framing/Rough-in | 11/1/2006 | 11/2/2006 | 11/2/2006 | A | DEFR |
Mike Jordan
|
|
|
rebar --harvey ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie. Special insp.
|
BLD-Other | 10/27/2006 | 10/31/2006 | 10/31/2006 | A | PART |
Mike Jordan
|
|
|
mel Note: late morning - rebar masonary; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. wip on masonry wall at garage.
|
BLD-Other | 10/27/2006 | 10/30/2006 | 10/30/2006 | A | DEFR |
Mike Jordan
|
|
|
mel Note: late morning - rebar masonary; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. Special insp. on masonry.
|
BLD-Footing | 10/25/2006 | 10/26/2006 | 10/26/2006 | A | PART |
Jim Sly
|
|
|
Nel, late morning please; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt CMU wall.....4' lift, up to 8' level.....OK pending MTI special insp, tests, and approvals.
|
BLD-Framing/Rough-in | 10/23/2006 | 10/24/2006 | 10/24/2006 | A | PART |
Mike Jordan
|
|
|
masonary wall insp-- mel ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie. 1st grout placement, 0 to 4ft. elev. at garage portion of station. work will have special insp.
|
BLD-Foundation | 10/13/2006 | 10/16/2006 | 10/16/2006 | A | PASS |
Mike Jordan
|
|
|
mel; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
BLD-Footing | 10/3/2006 | 10/3/2006 | 10/3/2006 | P | PART |
Mike Jordan
|
|
|
mel; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. Footings for dumpster, generator, and storage enclosures.
|
BLD-Foundation | 9/6/2006 | 9/7/2006 | 9/7/2006 | A | PASS |
Mike Jordan
|
|
|
Mel; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
|
BLD-Foundation | 9/6/2006 | 9/6/2006 | 9/6/2006 | P | PART |
Mike Jordan
|
|
|
wip. perimeter stemwall. Needs to tie verts for cmu walls.
|
BLD-Footing | 8/28/2006 | 8/29/2006 | 8/29/2006 | A | PART |
Mike Jordan
|
|
|
mel ; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley. perimeter footings. Missing verts at 8 inch to 12 inch wall intersection. Will install and check on stemwall insp.
|