(CCMG - CONTRACTOR RCE-54) (BOISE - 2ND FLR REMODEL) Minor remodel to construct 11 new offices, 4 small conference rooms, a board room, a file room, and a copy/print room in the north half of the second floor in an existing high-rise building per approved plans. (NOTE: This floor is actually what is typically called the third floor.) This floor will actually be vacant at this time to prepare for future work (asbestos removal, new sprayed fire-resistant materials, new sprinkler system installation, new ceilings, etc...) under a separate permit per an Upgrade Agreement on file. Work under this permit to include some new noncombustible interior walls, new interior doors, interior finish, some new counters/casework, accessible door hardware on the entire floor, fire alarm work, mechanical work, and electrical work. Existing ceiling will remain for now. This is a Scope of Work Permit. A Letter of Completion is to be issued when done. NOTE: This building is currently only fire sprinklered in the basement and on the upper penthouse level but will be fully fire sprinklered by January of 2011 per an Upgrade Agreement on file. JCB
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final12/27/200612/28/200612/28/2006APASS
DetailsDave Hannah
mike ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
DOC - Permit Finaled12/28/200612/28/200612/28/2006PPASS
DetailsDave Hannah
FIRE-Final Inspection12/27/200612/27/200612/27/2006PPASS
DetailsForrest France
Fire life safety inspection passed.
BLD-Final12/4/200612/4/200612/5/2006PNR
DetailsDave Hannah
mike ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
BLD-Final12/1/200612/4/200612/5/2006ANR
DetailsDave Hannah
mike ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
BLD-Other11/2/200611/2/200611/2/2006PPASS
DetailsDave Hannah
mike - sway bracing - as early as possible please ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
BLD-Other10/10/200610/11/200610/11/2006APART
DetailsDave Hannah
mike Note: above ceiling; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles ok to drop in panels after elec oks
BLD-Conference6/23/20066/23/20066/23/2006PPASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 6/23/2006 at 7:37:30 AM. Contact: ###-####. ok to cover walls