BLD-Final | 12/3/2007 | 12/5/2007 | 12/5/2007 | A | PASS |
Dave Hannah
|
|
|
Call ###-#### Michell 30 min. prior Internet Inspection Request from: Timothy Gammill
|
DOC - Permit Finaled | 12/5/2007 | 12/5/2007 | 12/5/2007 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 11/14/2007 | 11/16/2007 | 11/16/2007 | A | FAIL |
Dave Hannah
|
|
|
Please call Tim G. 30 min. prior ###-####. Internet Inspection Request from: Timothy Gammill tempered glass and returns on hand rail
|
Code Occupancy Approval | 11/14/2007 | 11/14/2007 | 11/14/2007 | P | PASS |
Michael Garner
|
|
|
site inspection complete - I found that the construction was completed according to approved plans/conditions of approval - PASS
|
BLD-Final | 11/7/2007 | 11/8/2007 | 11/8/2007 | A | NR |
Dave Hannah
|
|
|
Call Tim G. 30 min prior ###-#### Internet Inspection Request from: Timothy Gammilln needs code enforcement final
|
BLD-Wall cover | 8/7/2006 | 8/7/2006 | 8/7/2006 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 8/7/2006 at 7:25:48 AM. Contact: ###-####. ok to cover
|
BLD-Wall cover | 8/3/2006 | 8/4/2006 | 8/7/2006 | P | NR |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 8/3/2006 at 3:31:23 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 8/2/2006 | 8/3/2006 | 8/3/2006 | P | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 8/2/2006 at 4:40:32 PM. Contact: ###-####. still needs to add supports and braceing on old roof area of new over build ok to insulate
|
BLD-Energy code compliance | 8/2/2006 | 8/3/2006 | 8/3/2006 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 8/2/2006 at 4:40:59 PM. Contact: ###-####. seal package ok
|
BLD-Framing/Rough-in | 7/28/2006 | 8/2/2006 | 8/2/2006 | P | FAIL |
Mike Jordan
|
|
|
TIM nOTE: COVER; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. Needs to pass ri inspections. No approved plans on site. performed perliminary framing insp. needs to add blocking on floor joist at cantilever section. fur out interior nonloadbearing wall in basement (plumbers notched out to much.) Install squasah blocking under 2ply girder truss. Verify that AG girder truss was designed to carry additional load of existing roof. do not cover. Noted to contractor that when approved plans were on site that an official framing insp. would take place.
|
BLD-Energy code compliance | 7/28/2006 | 8/1/2006 | 7/31/2006 | A | CANC |
Dave Hannah
|
|
|
TIM; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Disp set to [CANC] by a contractor via Hello! on Jul 31 2006 4:37PM.
|
BLD-Foundation | 5/2/2006 | 5/3/2006 | 5/3/2006 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 5/2/2006 at 5:02:32 PM. Contact: ###-####.
|
BLD-Footing | 4/28/2006 | 5/1/2006 | 5/1/2006 | A | PASS |
Dave Hannah
|
|
|
jed; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|