BLD-Final | 12/14/2006 | 12/15/2006 | 12/15/2006 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 12/14/2006 at 11:26:18 AM. Contact: ###-####. ok for perm occ
|
FIRE-Final Inspection | 12/14/2006 | 12/15/2006 | 12/15/2006 | A | PASS |
Forrest France
|
|
|
Correction notice items have been verified for completion, fire life safety inspection passed.
|
FIRE-Final Inspection | 11/28/2006 | 11/28/2006 | 11/28/2006 | A | FAIL |
Forrest France
|
|
|
Need approved door hardware at the server room and vault, also need to re-install door closures at the elevator lobby doors.
|
FIRE-Conference | 11/20/2006 | 11/20/2006 | 11/20/2006 | P | DONE |
Forrest France
|
|
|
Confrence to discuss door hardware and project scheduled final completion dates.
|
BLD-Other | 10/31/2006 | 10/31/2006 | 11/1/2006 | A | DONE |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 10/31/2006 at 7:11:26 AM. Contact: ###-####.
|
BLD-Other | 10/31/2006 | 10/31/2006 | 10/31/2006 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 10/31/2006 at 7:11:26 AM. Contact: ###-####. Grid OK in Reception and office ?
|
BLD-Framing/Rough-in | 10/9/2006 | 10/10/2006 | 10/10/2006 | A | PASS |
Dave Hannah
|
|
|
mike-- 2nd floor of key bank bld; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie ok to cover walls
|