Permanent Occupancy | | 9/14/2006 | 9/14/2006 | | DONE |
|
|
|
|
BLD-Final | 8/30/2006 | 8/30/2006 | 8/30/2006 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 8/30/2006 at 10:55:11 AM. Contact: ###-####. ok for temp occ ok for perm occ after plumbing gos perm
|
FIRE-Final Inspection | 8/30/2006 | 8/30/2006 | 8/30/2006 | P | PASS |
Forrest France
|
|
|
c/n items have been completed, inspection passed.
|
FIRE-Final Inspection | 8/28/2006 | 8/29/2006 | 8/29/2006 | A | FAIL |
Forrest France
|
|
|
The project related fire sprinkler and fire alarm permits must be inspected, approved and finaled prior to BLD life safety final. Noted manual thumbturn to be removed at office door.
|
FIRE-Sprinkler Rough-in | 8/28/2006 | 8/29/2006 | 8/29/2006 | A | PART |
Forrest France
|
|
|
Inspection request was for the fire sprinklers which needs to be called in under the appropriate FIR permit number. Noted that OH rough-in is satisfactory, need to provide a current annual inspection certification for the existing system riser.
|
BLD-Wall cover | 8/8/2006 | 8/9/2006 | 8/9/2006 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 8/8/2006 at 3:40:54 PM. Contact: ###-####. ok to cover int walls
|