BLD-Final | 10/25/2006 | 10/25/2006 | 10/25/2006 | P | PASS |
Mike Jordan
|
|
|
bradeon; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
Permanent Occupancy | | 10/25/2006 | 10/25/2006 | | DONE |
|
|
|
|
FIRE-Final Inspection | 10/23/2006 | 10/23/2006 | 10/23/2006 | P | PASS |
Forrest France
|
|
|
Visual indicator and signage above the main entry/exit to be verified at structural final.
|
BLD-Framing/Rough-in | 10/23/2006 | 10/23/2006 | 10/23/2006 | P | PASS |
Mike Jordan
|
|
|
brayden - note: drop ceiling tiles insp. ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith. All issues have been resolved regarding the ceiling grid.
|
BLD-Energy code compliance | 10/23/2006 | 10/23/2006 | 10/23/2006 | P | DONE |
Mike Jordan
|
|
|
brayden - note: drop ceiling tiles insp. ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith. Energy code insp never called in, however, contractor did produce invoice noting insul type and labor for job. Also noted that attic insul was completed as per plan.
|
BLD-Other | 10/18/2006 | 10/20/2006 | 10/20/2006 | A | NR |
Mike Jordan
|
|
|
braymen - Note: ceiling grid; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. No ceiling plan for grid.
|
BLD-Framing/Rough-in | 9/13/2006 | 9/14/2006 | 9/14/2006 | A | PASS |
Mike Jordan
|
|
|
brayden- call 1/2 hr prior to meet there; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley. ok to insul.
|