BLD-Final | 12/5/2006 | 12/6/2006 | 12/6/2006 | A | PASS |
Mike Jordan
|
|
|
ben - call for access ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
DOC - Permit Finaled | 12/6/2006 | 12/6/2006 | 12/6/2006 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Energy code compliance | 10/5/2006 | 10/6/2006 | 10/6/2006 | A | PASS |
Mike Jordan
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. All framing issues have been resolved. Will need to check landing and tempered glass at final.
|
BLD-Framing/Rough-in | 10/2/2006 | 10/4/2006 | 10/4/2006 | P | FAIL |
Mike Jordan
|
|
|
###-#### - michael. Finish nailing simpson hangar at 2 ply girder truss in garage. Provide fireblocking at furout wall up stairs at tub shower stall. Temp glass required at window above tub west wall upstairs. Need to provide engineering sub 2x6 framed wall at entry for 2x4 wall. provide landing at front door no more than 1.5 inch below threshhold.
|
BLD-Footing | 9/5/2006 | 9/5/2006 | 9/5/2006 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 9/5/2006 at 7:19:46 AM. Contact: ###-####. Column pad footings were not built on either side of garage as redlined. Concrete contractor noted that he would get them installed.
|
BLD-Footing | 8/25/2006 | 8/28/2006 | 8/28/2006 | P | CANC |
Mike Jordan
|
|
|
matt; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. canc. by contractor.
|