Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberBLD06-02366
StatusFinaled
Name MICRON TECHNOLOGY INC
Site Address 8000 S FEDERAL WAY
Project Name 
Customer NumberC9897
ePlanReviewNo
Description
Micron Building #3 - (C9897) - RDA Bay Remodel - Change cleanroom wall panel configuration to line up the north and south walls of RDA 101N, reconfigure the east wall of RDA 101N, to replace a single door with an 8086 double door at the east wall of Plenum 301. Replace the door at the east wall of Plenum 302 and the egress door at the south end of Corridor 101P. To install two new return air chases at the east side of Corridor 101P, north of grid line 14. This permit is also to excavate the area below RDA 101N and install new 3'-0" high reinforced concrete retaining walls and 10" concrete floor to accomodate new raised floor system. plenumarrangement and doors exiting the area.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final1/2/20071/4/20071/4/2007APASS
DetailsJim Storey
Phone #: ###-#### Internet Inspection Request from: Greg Kirkes
DOC - Permit Finaled1/4/20071/4/20071/4/2007PPASS
DetailsJim Storey
BLD-Final12/18/200612/22/200612/22/2006PNR
DetailsJim Storey
Final this project including life safety for occupancy. All related permits have been completed, letter of final affedavit from MTI is completed.; Phone #: ###-#### Internet Inspection Request from: Greg Kirkes
FIRE-Final Inspection12/22/200612/22/200612/22/2006PPASS
DetailsForrest France
Fire life safety is satisfactory, inspection passed.
BLD-Final12/11/200612/15/200612/13/2006PCANC
DetailsJim Storey
Complete final inspection ; Phone #: ###-#### Internet Inspection Request from: Greg Kirkes Inspection cancelled from web by: Greg Kirkes
BLD-Conference11/21/200611/22/200611/22/2006APART
DetailsJim Storey
apply for temporary occupancy in RDA bay 1 for production.; Phone #: ###-#### Internet Inspection Request from: Greg Kirkes
BLD-Conference11/17/200611/21/200611/21/2006PCANC
DetailsJim Storey
Final inspection for RDA remodel.; Phone #: ###-#### Internet Inspection Request from: Greg Kirkes Inspection cancelled from web by: Greg Kirkes
BLD-Conference11/1/200611/3/200611/3/2006APART
DetailsJim Storey
Inspect ceiling areas and under floor systems.; Phone #: ###-#### Internet Inspection Request from: Greg Kirkes need fire stopping at coridor wall next to fire dampered duct two ele penatrations.
BLD-Conference10/11/200610/12/200610/12/2006APASS
DetailsJim Storey
Meet Jim Gilmore in 25, inspect drywall for skining in B3. ; Phone #: ###-#### Internet Inspection Request from: Greg Kirkes
BLD-Concrete10/9/200610/11/200610/11/2006PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 10/9/2006 at 3:11:16 PM. Contact: ###-####.pwsi
BLD-Concrete10/9/200610/10/200610/11/2006PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 10/9/2006 at 3:10:10 PM. Contact: ###-####.pwsi
BLD-Footing10/2/200610/5/200610/5/2006PPASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 10/2/2006 at 2:46:37 PM. Contact: ###-####.si
BLD-Footing10/2/200610/4/200610/4/2006PPART
DetailsJim Sly
Scheduled by a contractor via Hello! on 10/2/2006 at 2:46:17 PM. Contact: ###-####.
OK pending MTI special insp, tests and approvals.