FIRE-Final Inspection | 12/13/2006 | 12/14/2006 | 12/14/2006 | A | CANC |
Troy Cobbley
|
|
|
Wrong inspection number called in.
|
BLD-Final | 12/11/2006 | 12/12/2006 | 12/12/2006 | P | PASS |
Mike Jordan
|
|
|
renny ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
FIRE-Final Inspection | 11/29/2006 | 11/29/2006 | 11/29/2006 | P | PASS |
Troy Cobbley
|
|
|
life safety finaled
|
Permanent Occupancy | | 11/29/2006 | 11/29/2006 | | DONE |
|
|
|
|
Permanent Occupancy | | 11/23/2006 | 11/23/2006 | | DONE |
|
|
|
|
BLD-Final | 11/21/2006 | 11/22/2006 | 11/22/2006 | A | PASS |
Mike Jordan
|
|
|
BOB; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. Temp occ granted. Will be ok for perm occ once life/safety has finaled. Shell and core was finaled yesterday.
|
FIRE-Final Inspection | 11/21/2006 | 11/22/2006 | 11/22/2006 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given with dave hannimans permission until the fire alarm permit is inspected and finaled. The hvac unit has been locked out at the disconnect and I have the key. All other life safety items are ok.
|
FIRE-Final Inspection | 11/20/2006 | 11/20/2006 | 11/20/2006 | P | FAIL |
Troy Cobbley
|
|
|
Provide door hardware, no manual flush bolts at the double office doors, test exit signs and emergency lights and provide a fire alarm permit for the duct detector tie in to the existing, but new fire alarm system.
|
BLD-Framing/Rough-in | 11/3/2006 | 11/6/2006 | 11/6/2006 | A | PASS |
Mike Jordan
|
|
|
bob ; Phone #: ###-#### note: suite 100 - Internet Inspection Request from: Patricia Smith. Interior framed walls only.
|