Information based on query as of Friday, August 16, 2024.
Permit Information
Permit NumberBLD06-03043
StatusFinaled
Name AC CONSTRUCTION
Site Address 1199 W SHORELINE LN
Project NameRIVER PARK BLDG
Customer Number 
ePlanReviewNo
Description
(RCE-3673) (RIVER PARK BLDG - UPGRADE) To install 60 minute minimum rated/450 degree max. temperature rated doors on hold-open at the elevator openings on all floors to comply with an Alternate Approval on an expired Upgrade Agreement per approved plans. This is the last permitted work to be completed and approved to comply with the Upgrade Agreement. Other work permitted under BLD06-02914 should also be completed and approved. This is a Scope of Work Permit. A Letter of Completion is to be issued when done. NOTE: This building is fully fire sprinklered for one-hour substitution. JCB
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final8/7/20078/8/20078/7/2007ADONE
DetailsDave Hannah
Fire and electrical have been completed. LC issued.
DOC - Permit Finaled  8/7/2007 DONE
BLD-Final7/27/20077/30/20077/30/2007PNR
DetailsDave Hannah
doc Phone #: ###-#### everything ok but needs fire sign offs
FIRE-Final Inspection7/27/20077/30/20077/30/2007AFAIL
DetailsForrest France
Fire alarm work did not pass inspection, also need to install smoke seals at all three doors.
BLD-Other5/15/20075/15/20075/15/2007PPART
DetailsBob Archibald
Site visit no new work in progres. Phone call to Davina who reports that wrong doors were shipped and replacements were reported 3-4 weeks out on the last week of April. All other permits and work progress on hold, waiting to hear from contractor.
BLD-Conference3/6/20073/6/20073/6/2007PPART
DetailsDave Hannah
Phone conference with Davina (property manager), doors have been backordered and are scheduled to be delivered 3rd week of March. Site visit confirmed no work had commenced.
BLD-Aging Inspection3/1/20073/1/20073/6/2007PPART
DetailsDave Hannah
Doors backorderd work scheduled to begin later in March.