BLD-Final | 6/30/2008 | 6/30/2008 | 6/30/2008 | P | DONE |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 6/30/2008 at 7:32:20 AM. Contact: ###-####.
|
BLD-Final | 6/30/2008 | 6/30/2008 | 6/30/2008 | P | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 6/26/2008 at 11:13:45 PM. Contact: ###-####. temp. hand/guardrails for now on outside,, need to finish fireplace also,, c of c issued
|
DOC - Permit Finaled | 6/30/2008 | 6/30/2008 | 6/30/2008 | P | PASS |
Tony Young
|
|
|
c of c issued
|
Code Occupancy Approval | 6/30/2008 | 6/30/2008 | 6/30/2008 | P | PASS |
Michael Garner
|
|
|
site inspection complete - I found that the construction has been completed according to approved plans and permits - PASS
|
BLD-Final | 6/27/2008 | 6/30/2008 | 6/30/2008 | A | NR |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 6/26/2008 at 11:13:45 PM. Contact: ###-####.
|
BLD-Final | 6/26/2008 | 6/27/2008 | 6/27/2008 | A | NR |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 6/26/2008 at 11:13:45 PM. Contact: ###-####. need zoning signoff 1st,, on site conf only
|
BLD-Final | 6/24/2008 | 6/26/2008 | 6/26/2008 | A | NR |
Tony Young
|
|
|
anne Phone #: ###-#### need trades 1st
|
BLD-Energy code compliance | 8/27/2007 | 8/28/2007 | 8/28/2007 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 8/27/2007 at 11:41:40 AM. Contact: ###-####. ok for cover w/ conditions
|
BLD-Framing/Rough-in | 8/23/2007 | 8/23/2007 | 8/23/2007 | P | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 8/23/2007 at 10:55:01 AM. Contact: ###-####. ceilings meet at 65%,, ok to insulate
|
FIRE-Conference | 8/7/2007 | 8/7/2007 | 8/7/2007 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 8/7/2007 at 10:25:16 AM. Contact: ###-####. smoke det. locations,, need 7ft ceilings,, sent back to plan review
|
BLD-Conference | 4/13/2007 | 4/13/2007 | 4/13/2007 | P | PART |
Tony Young
|
|
|
trent ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith beam bearing ?s
|
BLD-Foundation | 12/18/2006 | 12/20/2006 | 12/20/2006 | P | FAIL |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 12/18/2006 at 10:01:34 AM. Contact: ###-####. poured yesterday or before
|
BLD-Footing | 12/11/2006 | 12/11/2006 | 12/11/2006 | P | PASS |
Dave Hannah
|
|
|
trent ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
BLD-Footing | 12/6/2006 | 12/7/2006 | 12/7/2006 | A | FAIL |
Dave Hannah
|
|
|
rick; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles ground is frozen
|