Permit Information
Permit NumberBLD07-00236
StatusFinaled
Name MARK LASALLE
Site Address 1810 W LEMP ST
Project Name 
Customer Number 
ePlanReviewNo
Description
"UPDATED EXISTING PERMIT ON 6/15/07 AS PER APPROVED PLANS AND ALL RED-LINING. (SRZ) This extensive interior remodel project is for the removal of the interior wall coverings to allow for the upgrade of the electrical and plumbing systems, insulating the exterior walls in the main level and the basement where a new bathroom and laundry room will be created, adding egress windows. Firring out of select basement walls and select interior partition modifications throughout. Separate electrical and plumbing permits are required. The energy code will be address at this time with insulation only and the existing windows will be upgraded as funds allow. R1CH ok per Colleen Carroll. All per the approved plans as marked and plan review notes. pep
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final7/20/20127/23/20127/23/2012APASS
DetailsTony Young
or ###-#### Mark LaSalle Phone #: ###-####
DOC - Permit Finaled7/23/20127/23/20127/23/2012PPASS
DetailsTony Young
done
BLD-Aging Inspection6/21/20126/21/20126/25/2012 PASS
DetailsTony Young
BLD-Final12/24/200912/28/200912/28/2009AFAIL
DetailsTony Young
expired
DOC - Permit Expired12/28/200912/28/200912/28/2009PPASS
DetailsTony Young
BLD-Framing/Rough-in12/23/200912/23/200912/24/2009PPEND
DetailsTony Young
check status
will re-schedule
BLD-Aging Inspection12/16/200912/16/200912/23/2009 PEND
DetailsTony Young
BLD-Final12/26/200712/26/200712/26/2007PPART
DetailsJim Storey
mark Phone #: ###-#### hand rails in and out need vervied as well as window well back fill to eleavate ladder provision. ok to move in blongings and call for reinsption of these idems.
Code Occupancy Approval12/26/200712/26/200712/26/2007PPASS
DetailsMichael Garner
site inspection complete - I observed that the construction has been completed according to the approved Design Review/Plans - PASS
Code Occupancy Approval  12/19/2007 FAIL
Front window frames not completed as of 1000 hrs; basement window wells not filled in
BLD-Wall cover10/5/200710/5/200710/5/2007APASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 10/5/2007 at 2:07:01 AM. Contact: ###-####.
BLD-Energy code compliance10/5/200710/5/200710/5/2007PPASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 10/5/2007 at 2:07:01 AM. Contact: ###-####.
BLD-Framing/Rough-in10/2/200710/3/200710/3/2007APASS
DetailsTony Young
Scheduled by a contractor via Hello! on 10/2/2007 at 11:04:07 PM. Contact: ###-####.
ok to insulate all now
BLD-Conference8/16/20078/17/20078/17/2007APART
DetailsTony Young
Mark; Phone #: ###-#### Internet Inspection Request from: Hattie James
ok to insulate upper area exterior walls without mechanical,, wanted to work over the weekend and mech parts wont be in untill next week,, conf on job
BLD-Footing6/28/20076/28/20076/28/2007PDONE
DetailsTony Young
mark Phone #: ###-####
BLD-Footing6/20/20076/20/20076/20/2007PPASS
DetailsJim Sly
lance; Phone #: ###-#### Internet Inspection Request from: Victoria Apatang
BLD-Conference3/16/20073/16/20073/16/2007PPART
DetailsTony Young
marc; Phone #: ###-#### Internet Inspection Request from: Victoria Beallgeneral conf on job, old house,, will need headers,, may want to add to permit for front porch,, need to see plan review and zoning
BLD-Conference3/13/20073/14/20073/14/2007ACANC
DetailsTony Young
Samuel; Phone #: ###-#### Internet Inspection Request from: Stacie Backus
canc per owner