BLD-Final | 6/27/2007 | 6/27/2007 | 6/27/2007 | P | PASS |
Jim Sly
|
|
|
matt Phone #: ###-#### OK for Perm Occ.
|
FIRE-Final Inspection | 6/26/2007 | 6/27/2007 | 6/27/2007 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. I notified Matt, the contractor that if the access controled egress doors are installed they would have to comply with Chapter 10 of the IFC and IBC.
|
FIRE-Final Inspection | 6/19/2007 | 6/20/2007 | 6/20/2007 | A | FAIL |
Troy Cobbley
|
|
|
repair the nonfunctioning exit light and provide approved hardware on the exterior exit doors. If the access controled egress items are utilized a separate fire alarm permit will be required for the interconnection.
|
BLD-Framing/Rough-in | 5/9/2007 | 5/9/2007 | 5/9/2007 | P | PART |
Jim Sly
|
|
|
matt ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith Framing OK except............Demising wall moved to the North....allowing for more square footage. C/N.... Architect to resubit modifed plan to Planning and Devel. services for approval. Need new fire sprinkler plan submitted for approval.
|