BLD-Aging Inspection | 2/11/2008 | 2/11/2008 | 2/11/2008 | | PASS |
Jim Storey
|
|
|
all sign off ok
|
DOC - Permit Finaled | 2/11/2008 | 2/11/2008 | 2/11/2008 | P | PASS |
Jim Storey
|
|
|
|
Code Occupancy Approval | 12/6/2007 | 12/6/2007 | 12/6/2007 | P | PASS |
Joe R Venneman
|
|
|
Landscaping and other exterior requirements finally are completed. Owner will spread the bark in the d/way this weekend due to wet conditions now.
|
BLD-Final | 10/15/2007 | 10/18/2007 | 10/18/2007 | P | PART |
Jim Storey
|
|
|
jack Phone #: ###-#### temp ok pending p/z and pw
|
FIRE-Final Inspection | 10/18/2007 | 10/18/2007 | 10/18/2007 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 10/17/2007 | 10/18/2007 | 10/18/2007 | A | FAIL |
Troy Cobbley
|
|
|
Door hardware is still incorrect
|
FIRE-Final Inspection | 10/15/2007 | 10/16/2007 | 10/16/2007 | P | FAIL |
Forrest France
|
|
|
Provide two fire extinguishers and install per review notes and discussion, manual thumbturn at the main entry/exit door is not allowed, provide approved hardware at three exit doors, EM lights and exit signs tested okay.
|
BLD-Energy code compliance | 8/27/2007 | 8/28/2007 | 8/28/2007 | A | PASS |
Jim Sly
|
|
|
Jack; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt Trusses and beam OK too.
|
BLD-Framing/Rough-in | 8/23/2007 | 8/24/2007 | 8/24/2007 | A | PART |
Jim Storey
|
|
|
Jack; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt no truss engineering on site need to review at insulation insp. as well as post and beam support at jack trusses at hall not in place.
|
BLD-Foundation | 7/2/2007 | 7/3/2007 | 7/3/2007 | A | PART |
Mike Jordan
|
|
|
matt; Phone #: ###-#### Internet Inspection Request from: Victoria Apatang. wip. Drilling in progress into existing stewmwall. ok to place conc.
|
BLD-Footing | 6/29/2007 | 7/2/2007 | 7/2/2007 | A | PASS |
Jim Sly
|
|
|
matt; Phone #: ###-#### Internet Inspection Request from: Victoria Apatang
|
BLD-Footing | 6/28/2007 | 6/29/2007 | 6/29/2007 | A | FAIL |
Mike Jordan
|
|
|
matt Phone #: ###-####. Work is not far enough along to pass. Needs to clean out bottom of footing (vegetation, tree roots.) remove excess dirt away from existing foundation so tie in can be made. Will also have to remove vegetation from interior slab area before fill material can be placed. Due to amount of fill material needed, compaction testing will be performed. Contractor to recall footing insp.
|