BLD-Final | 12/6/2007 | 12/6/2007 | 12/7/2007 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Internet Inspection Request from: Gary Band. ok for perm occ.
|
BLD-Conference | 12/6/2007 | 12/7/2007 | 12/7/2007 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Internet Inspection Request from: Gary Band
|
BLD-Final | 11/28/2007 | 11/28/2007 | 11/28/2007 | P | PART |
Mike Jordan
|
|
|
Gary Phone #: ###-####. Temp occ granted. Will be ok for per occ once shell and core are signed off.
|
BLD-Final | 11/27/2007 | 11/27/2007 | 11/27/2007 | P | NR |
Mike Jordan
|
|
|
Gary ###-####.
|
FIRE-Final Inspection | 11/27/2007 | 11/27/2007 | 11/27/2007 | P | PASS |
Troy Cobbley
|
|
|
life safety passed.
|
BLD-Framing/Rough-in | 11/20/2007 | 11/21/2007 | 11/21/2007 | A | PASS |
Mike Jordan
|
|
|
gary--ceiling grid Phone #: ###-####. grid ok.
|
BLD-Framing/Rough-in | 11/19/2007 | 11/19/2007 | 11/19/2007 | A | NR |
Mike Jordan
|
|
|
Gary ###-####--ceiling grid inspection please. Still needs mech.
|
BLD-Framing/Rough-in | 11/15/2007 | 11/16/2007 | 11/16/2007 | P | FAIL |
Mike Jordan
|
|
|
gary - ceiling grid Phone #: ###-####. Needs mech ri insp, needs to provide ceiling grid details from architect.
|
BLD-Energy code compliance | 11/1/2007 | 11/1/2007 | 11/1/2007 | P | PASS |
Mike Jordan
|
|
|
gary - reinspection Phone #: ###-####
|
BLD-Framing/Rough-in | 10/30/2007 | 10/31/2007 | 10/31/2007 | A | PASS |
Mike Jordan
|
|
|
gary Phone #: ###-####
|
BLD-Foundation | 8/28/2007 | 8/29/2007 | 8/29/2007 | P | PART |
Mike Jordan
|
|
|
Gary; Phone #: ###-#### Internet Inspection Request from: Hattie James . Interior footings, wip. Will be done with sog.
|