BLD-Final | 11/21/2007 | 11/21/2007 | 11/21/2007 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 11/21/2007 at 10:54:14 AM. Contact: ###-####.
|
DOC - Permit Finaled | 11/21/2007 | 11/21/2007 | 11/21/2007 | P | PASS |
Mike Jordan
|
|
|
letter of compliance was issued. shell and core ok. verifid all sign offs.
|
BLD-Energy code compliance | 11/21/2007 | 11/21/2007 | 11/21/2007 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 11/21/2007 at 10:54:14 AM. Contact: ###-####.
|
BLD-Final | 11/15/2007 | 11/16/2007 | 11/16/2007 | P | NR |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 11/15/2007 at 3:59:00 PM. Contact: ###-####.
|
FIRE-Final Inspection | 11/15/2007 | 11/16/2007 | 11/16/2007 | A | PASS |
Troy Cobbley
|
|
|
LIfe safety for the shell passed.
|
FIRE-Final Inspection | 11/7/2007 | 11/8/2007 | 11/8/2007 | A | FAIL |
Troy Cobbley
|
|
|
Provide address on both sides of building where is can be viewable as discussed, provide power so the exit sign and emergency lighting can be tested.
|
BLD-Framing/Rough-in | 8/20/2007 | 8/21/2007 | 8/21/2007 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/20/2007 at 1:09:19 PM. Exterior shear, Roof diaphargm and holdowns ok. Interior framing and trusses ok.
|
BLD-Framing/Rough-in | 8/8/2007 | 8/9/2007 | 8/9/2007 | A | CANC |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/8/2007 at 1:50:00 PM. Contact: ###-####.
|
BLD-Foundation | 6/29/2007 | 7/2/2007 | 7/2/2007 | A | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 6/29/2007 at 4:23:09 PM. Contact: ###-####.
|
BLD-Footing | 6/26/2007 | 6/27/2007 | 6/27/2007 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 6/26/2007 at 4:15:23 PM. Contact: ###-####. Project to have special insp. Soils ok as per geo-tech.
|