FIRE-Final Inspection | 8/31/2007 | 9/4/2007 | 9/4/2007 | A | PASS |
Forrest France
|
|
|
Fire life safety finaled.
|
FIRE-Final Inspection | 8/31/2007 | 8/31/2007 | 8/31/2007 | P | PASS |
Forrest France
|
|
|
Corrections verified for completion, fire life safety inspection passed.
|
BLD-Final | 8/30/2007 | 8/31/2007 | 8/31/2007 | P | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Internet Inspection Request from: Carrie Van Houten OK for Perm Occ. :) 1/2v a gud w/nd.
|
FIRE-Final Inspection | 8/30/2007 | 8/31/2007 | 8/31/2007 | A | FAIL |
Forrest France
|
|
|
Missing EM lighting at the stock area, one exit sign and emergency light at the main entry needs to be repaired, exit door from the storage area is difficult to open.
|
FIRE-Final Inspection | 8/28/2007 | 8/30/2007 | 8/30/2007 | P | CANC |
Forrest France
|
|
|
carrie - fire life safety Phone #: ###-####
|
BLD-Other | 8/15/2007 | 8/16/2007 | 8/16/2007 | A | PART |
Jim Storey
|
|
|
need inspection for ceiling grid, please call prior to arrival Thanks. Phone #: ###-#### Internet Inspection Request from: Carrie Van Houten check for spreader bars and hvac wire at final,
|
BLD-Framing/Rough-in | 7/27/2007 | 7/30/2007 | 7/30/2007 | P | PASS |
Jim Sly
|
|
|
please call Carrie at ###-#### to meet on location. Thanks. Internet Inspection Request from: Carrie Van Houten
OK'd framing......with Minor door location changes shown on 8 1/2 x 11 detail from Architech......( Double front and double corridor doors moved approx 5')......probably not enough change of plan to archive. Need to verify MTI inspection of steel columns, epoxy bolting to CMU and solid grout fill around new double rear exit doors befor final. (had it....forgot to bring for frame insp). :)
|
FIRE-Conference | 7/24/2007 | 7/25/2007 | 7/27/2007 | A | DONE |
Forrest France
|
|
|
On site visit to discuss project related fire alarm and sprinkler permit issues.
|
BLD-Framing/Rough-in | 7/20/2007 | 7/23/2007 | 7/23/2007 | A | NR |
Jim Storey
|
|
|
Phone #: ###-#### Internet Inspection Request from: Carrie Van Houten
|