BLD-Energy code compliance | 10/8/2007 | 10/8/2007 | 10/8/2007 | P | PASS |
Mike Jordan
|
|
|
doug - insulation Phone #: ###-####. Airseal package compltetd ok to cover.
|
BLD-Energy code compliance | 10/4/2007 | 10/4/2007 | 10/4/2007 | P | FAIL |
Mike Jordan
|
|
|
doug - insulation Phone #: ###-####. Airseal package not complete. Needs to caulk wires at boxes.
|
BLD-Framing/Rough-in | 9/24/2007 | 9/24/2007 | 9/24/2007 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 9/24/2007 at 8:18:55 AM. Contact: ###-####. Needs to complete airseal package. ok to insul.
|
BLD-Footing | 8/15/2007 | 8/16/2007 | 8/16/2007 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/15/2007 at 4:14:35 PM. Contact: ###-####.
|
BLD-Footing | 8/1/2007 | 8/2/2007 | 8/2/2007 | A | PART |
Mike Jordan
|
|
|
eric Phone #: ###-####. wip. monolithic placement of footing and stemwall.
|