Permit Information
Permit NumberBLD07-02079
StatusFinaled
Name MIKE COOK
Site Address 4000 W PLUM ST
Project Name 
Customer Number 
ePlanReviewNo
Description
This project is for the remodel of and the addition of 1000s.f. of living space to an existing 1326s.f. single family dwelling. 440s.f. of living space will be a slab on grade and 400s.f. of the living space will be over the new attached 460s.f. 2-car garage. "The permit holder is responsible to comply with current wall bracing requirements as adopted by Boise City." R-1C setbacks ok per Colleen Carroll. Separate electrical, plumbing, mechanical and ESC permits are required. All per the approved plans as marked REScheck, Engineering with engineer's details along with the plan review notes. pep
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final2/13/20082/13/20082/13/2008PPASS
DetailsTony Young
mike - please call 1 hr prior to inspection Phone #: ###-####
DOC - Permit Finaled2/13/20082/13/20082/13/2008PPASS
DetailsTony Young
c of c issued
BLD-Final1/31/20082/1/20082/1/2008ANR
DetailsMike Jordan
mike - please call 1/2 hr prior to inspection Phone #: ###-####. Needs mech final to pass. Mike was contacted and informed of failed mech. final.
BLD-Wall cover11/1/200711/2/200711/2/2007APASS
DetailsTony Young
mike; Phone #: ###-#### Internet Inspection Request from: Barbara Stitt
BLD-Other10/30/200710/31/200710/31/2007AFAIL
DetailsDave Hannah
mike Note: cover up Phone #: ###-#### seal package not installed
BLD-Framing/Rough-in10/11/200710/11/200710/11/2007PPART
DetailsTony Young
mike Phone #: ###-####
c/n on tag,, ok to insulate
BLD-Conference10/1/200710/2/200710/2/2007APASS
DetailsTony Young
mike Phone #: ###-####
general conf.
BLD-Framing/Rough-in9/17/20079/17/20079/17/2007PNR
DetailsJim Storey
mike Phone #: ###-#### conf.
BLD-Foundation8/27/20078/28/20078/28/2007PPART
DetailsTony Young
Mike; Phone #: ###-#### Internet Inspection Request from: Hattie James
mono ok,, need to do ftg in front of garage when apron is poured,, wip
BLD-Foundation8/16/20078/20/20078/21/2007PPART
DetailsTony Young
Mike; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
wip on walls
BLD-Footing8/14/20078/15/20078/15/2007APART
DetailsTony Young
Mike, as early as possible please; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
new rebar put in,, wip
BLD-Footing8/13/20078/14/20078/14/2007AFAIL
DetailsTony Young
Mike; Phone #: ###-#### Internet Inspection Request from: Darla Downs
need to talk to struct engineer about soil, rebar being hot bent, etc