BLD-Final | 4/21/2008 | 4/21/2008 | 4/21/2008 | P | PASS |
Tony Young
|
|
|
steve Phone #: ###-####
|
DOC - Permit Finaled | 4/21/2008 | 4/21/2008 | 4/21/2008 | P | PASS |
Tony Young
|
|
|
|
Code Occupancy Approval | 4/21/2008 | 4/21/2008 | 4/21/2008 | P | PASS |
Michael Garner
|
|
|
site inspection complete - addition built according to approved plans and standard condtiions - PASS
|
BLD-Final | 4/18/2008 | 4/18/2008 | 4/21/2008 | P | NR |
Tony Young
|
|
|
steve Phone #: ###-#### final ok after zoning
|
BLD-Final | 4/17/2008 | 4/18/2008 | 4/18/2008 | A | NR |
Tony Young
|
|
|
steve Phone #: ###-#### NEED ZONING 1ST
|
BLD-Final | 4/16/2008 | 4/17/2008 | 4/17/2008 | A | NR |
Tony Young
|
|
|
steve Phone #: ###-#### conf. only,, need code enforcement 1st,, final is ok other than that
|
BLD-Framing/Rough-in | 3/7/2008 | 3/10/2008 | 3/10/2008 | A | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 3/7/2008 at 4:42:43 PM. Contact: ###-####.
|
BLD-Energy code compliance | 11/21/2007 | 11/26/2007 | 11/26/2007 | A | PASS |
Tony Young
|
|
|
Steve Phone #: ###-####
|
BLD-Framing/Rough-in | 11/16/2007 | 11/19/2007 | 11/19/2007 | A | PASS |
Tony Young
|
|
|
Steve, please call 15 minutes prior for access; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
|
BLD-Foundation | 9/20/2007 | 9/20/2007 | 9/20/2007 | P | PART |
Tony Young
|
|
|
CAL Phone #: ###-####
|
BLD-Footing | 9/19/2007 | 9/19/2007 | 9/19/2007 | P | PASS |
Tony Young
|
|
|
cal Phone #: ###-#### Note: call for where the plans are at - porta potty Ha Ha
|
BLD-Conference | 9/11/2007 | 9/12/2007 | 9/12/2007 | A | PASS |
Tony Young
|
|
|
Please call prior to inspection so he can meet ya there-=-steve; Phone #: ###-#### Internet Inspection Request from: Barbara Stitt conf on foundation,, old stone w/out much of ftg,, post and beam ok next to existing,, then addition walls and ftg tied into existing
|