BLD-Final | 11/26/2007 | 11/27/2007 | 11/27/2007 | A | PASS |
Mike Jordan
|
|
|
don note: EARLY mORNING Phone #: ###-####
|
DOC - Permit Finaled | 11/27/2007 | 11/27/2007 | 11/27/2007 | P | PASS |
Mike Jordan
|
|
|
Letter of compliance issued. Verified all sign offs.
|
FIRE-Final Inspection | 11/21/2007 | 11/26/2007 | 11/26/2007 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Final Inspection | 11/20/2007 | 11/21/2007 | 11/21/2007 | A | FAIL |
Troy Cobbley
|
|
|
Per the general contractor the needed a/v devices did not arrive via UPS as desired. Inspection is to be rescheduled.
|
FIRE-Final Inspection | 11/19/2007 | 11/20/2007 | 11/20/2007 | A | FAIL |
Troy Cobbley
|
|
|
The project related fire alarm permit needs finaled first.
|
FIRE-Final Inspection | 11/16/2007 | 11/19/2007 | 11/19/2007 | A | FAIL |
Troy Cobbley
|
|
|
The project related fire alarm permit needs finaled first.
|
FIRE-Final Inspection | 10/30/2007 | 10/30/2007 | 10/30/2007 | P | FAIL |
Troy Cobbley
|
|
|
A fire alarm permit is required for the work performed to accomodate the new wall layout. Strobes are overspaced in the shoe storage area and not mounted at the correct heights.
|
BLD-Framing/Rough-in | 10/11/2007 | 10/12/2007 | 10/12/2007 | A | PASS |
Mike Jordan
|
|
|
don Phone #: ###-####. Steel stud interior non load bearing walls, phase 2.
|
BLD-Framing/Rough-in | 9/21/2007 | 9/24/2007 | 9/24/2007 | A | PART |
Mike Jordan
|
|
|
don Phone #: ###-####. Interior framed wall for new shoe display. ok, (phase 1)
|
BLD-Conference | 9/17/2007 | 9/18/2007 | 9/18/2007 | A | DONE |
Mike Jordan
|
|
|
darren Phone #: ###-####
|