BLD-Final | 6/27/2008 | 6/27/2008 | 6/27/2008 | P | PASS |
Mike Jordan
|
|
|
|
DOC - Permit Finaled | 6/27/2008 | 6/27/2008 | 6/27/2008 | P | PASS |
Mike Jordan
|
|
|
Verified draft stop. Letter of completion issued.
|
FIRE-Final Inspection | 6/6/2008 | 6/6/2008 | 6/6/2008 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
Code Occupancy Approval | | | 5/29/2008 | | PASS |
Wm. Michael Meloy
|
|
|
Compliance met under revised landscaping plan Mar 2008
|
FIRE-Final Inspection | 5/28/2008 | 5/28/2008 | 5/28/2008 | P | FAIL |
Troy Cobbley
|
|
|
The fire extinguishers had not been installed, no address was installed and no one was one site to test the duct smoke detectors. Basically no inspection was performed.
|
BLD-Conference | 5/16/2008 | 5/19/2008 | 5/19/2008 | A | PASS |
Dave Hannah
|
|
|
Derrick Phone #: ###-####
|
BLD-Energy code compliance | 3/14/2008 | 3/14/2008 | 3/14/2008 | P | PASS |
Dave Hannah
|
|
|
derick - insulation Phone #: ###-####
|
BLD-Framing/Rough-in | 3/10/2008 | 3/10/2008 | 3/10/2008 | P | PASS |
Dave Hannah
|
|
|
DERICK Phone #: ###-#### ok to insulate
|
BLD-Other | 2/12/2008 | 2/19/2008 | 2/19/2008 | A | PASS |
Tony Young
|
|
|
derick Note: nailing Phone #: ###-#### roof and exterior ok to cover
|
BLD-Foundation | 12/26/2007 | 12/27/2007 | 12/27/2007 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 12/26/2007 at 8:46:51 AM. Contact: ###-####.
|
BLD-Foundation | 12/26/2007 | 12/26/2007 | 12/26/2007 | P | CANC |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 12/26/2007 at 8:46:51 AM. Contact: ###-####.
|
BLD-Footing | 12/20/2007 | 12/20/2007 | 12/20/2007 | P | DONE |
Dave Hannah
|
|
|
|
BLD-Footing | 12/19/2007 | 12/20/2007 | 12/20/2007 | A | PASS |
Dave Hannah
|
|
|
Aw ry Phone #: ###-####
|