BLD-Final | 4/4/2008 | 4/9/2008 | 4/9/2008 | A | PASS |
Tony Young
|
|
|
rob- call 1st for access Phone #: ###-####
|
DOC - Permit Finaled | 4/9/2008 | 4/9/2008 | 4/9/2008 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Final | 4/2/2008 | 4/4/2008 | 4/7/2008 | P | NR |
Tony Young
|
|
|
rob- call 1st for access Phone #: ###-####
|
BLD-Final | 3/31/2008 | 4/2/2008 | 4/2/2008 | P | CANC |
Tony Young
|
|
|
rob- call 1st for access Phone #: ###-####
|
BLD-Final | 3/27/2008 | 3/28/2008 | 3/31/2008 | P | NR |
Tony Young
|
|
|
rob- call 1st for access Phone #: ###-#### need handrail on ext
|
BLD-Final | 3/21/2008 | 3/27/2008 | 3/27/2008 | A | PART |
Tony Young
|
|
|
rob- call 1st for access Phone #: ###-#### need hand rail out front stairs to from driveway to front door area,, conf only,, wip on driveway
|
BLD-Grading Inspection | 3/24/2008 | 3/24/2008 | 3/24/2008 | P | DONE |
Terry Records
|
|
|
Final grading and drainage approved
|
BLD-Final | 3/20/2008 | 3/21/2008 | 3/21/2008 | P | NR |
Tony Young
|
|
|
rob- call 1st for access Phone #: ###-#### need concrete landings etc,
|
BLD-Conference | 3/19/2008 | 3/20/2008 | 3/20/2008 | A | PART |
Tony Young
|
|
|
rob- call 1st for access Phone #: ###-#### phone conf only
|
BLD-Conference | 3/18/2008 | 3/19/2008 | 3/19/2008 | A | PART |
Tony Young
|
|
|
rob- call 1st for access Phone #: ###-#### phone conf only,, will need to try to final by 3/21,, need trades, hillside etc.. will do walk through 3/20
|
BLD-Energy code compliance | 12/12/2007 | 12/12/2007 | 12/12/2007 | P | PASS |
Tony Young
|
|
|
traux Phone #: ###-####
|
BLD-Framing/Rough-in | 12/12/2007 | 12/12/2007 | 12/12/2007 | P | PASS |
Tony Young
|
|
|
traux Phone #: ###-#### Talked w/ Lloyd Pack, structural engineer,, all ok per plan now except manf panel on garage front,, but ok due to single story and against hill for less wind load
|
BLD-Framing/Rough-in | 12/10/2007 | 12/11/2007 | 12/12/2007 | P | NR |
Tony Young
|
|
|
traux Phone #: ###-####
|
BLD-Framing/Rough-in | 12/4/2007 | 12/4/2007 | 12/4/2007 | P | PART |
Tony Young
|
|
|
rob Phone #: ###-#### ok to insulate,, need eng letter of ok
|
BLD-Framing/Rough-in | 11/30/2007 | 12/4/2007 | 12/4/2007 | A | CANC |
Tony Young
|
|
|
rob Phone #: ###-####
|
BLD-Framing/Rough-in | 11/30/2007 | 11/30/2007 | 11/30/2007 | P | PART |
Tony Young
|
|
|
rob Phone #: ###-#### ok to cover exterior
|
BLD-Framing/Rough-in | 11/27/2007 | 11/28/2007 | 11/27/2007 | A | CANC |
Tony Young
|
|
|
rob - please call 1/2 hr prior to inspection Phone #: ###-####
|
BLD-Framing/Rough-in | 11/19/2007 | 11/20/2007 | 11/20/2007 | P | PART |
Tony Young
|
|
|
1:30 apt with rob and engineer Phone #: ###-#### conf w/ st. eng., and framer,, eng. will reinspect shear issues and provide letter of ok then I will look at interior shear
|
BLD-Framing/Rough-in | 11/15/2007 | 11/15/2007 | 11/15/2007 | P | FAIL |
Tony Young
|
|
|
rob - shear wall - approved plans on the job Phone #: ###-#### no plans on site ,not ready
|
BLD-Conference | 11/13/2007 | 11/14/2007 | 11/14/2007 | A | FAIL |
Tony Young
|
|
|
Rob (Jr.) ###-#### need plans on site to verify shear,, Tyvec is on,, did spot checks,, needs redone
|
BLD-Foundation | 9/28/2007 | 10/1/2007 | 10/1/2007 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 9/28/2007 at 1:35:46 PM. Contact: ###-####. wip
|
BLD-Footing | 9/26/2007 | 9/27/2007 | 9/27/2007 | A | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 9/26/2007 at 4:52:11 PM. Contact: ###-####.
|
BLD-Foundation | 9/26/2007 | 9/28/2007 | 9/27/2007 | P | CANC |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 9/26/2007 at 4:52:59 PM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Sep 27 2007 11:33AM.
|
BLD-Footing | 9/25/2007 | 9/25/2007 | 9/26/2007 | P | NR |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 9/25/2007 at 9:54:16 AM. Contact: ###-####.
|