BLD-Final | 12/23/2011 | 12/23/2011 | 12/23/2011 | P | PASS |
Dave Hannah
|
|
|
mike - please call 1/2 hr prior Phone #: ###-####
|
DOC - Permit Finaled | 12/23/2011 | 12/23/2011 | 12/23/2011 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 11/17/2011 | 11/17/2011 | 11/21/2011 | | PASS |
Dave Hannah
|
|
|
work in progress
|
BLD-Final | 8/18/2011 | 8/19/2011 | 8/19/2011 | A | PART |
Dave Hannah
|
|
|
mike - late morning please Phone #: ###-#### needs handrails and gaurd rail
|
BLD-Aging Inspection | 8/5/2011 | 8/5/2011 | 8/12/2011 | | PASS |
Dave Hannah
|
|
|
Talked with mike he will schedule a final next week
|
BLD-Aging Inspection | 3/16/2011 | 3/16/2011 | 3/22/2011 | | PASS |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 1/3/2011 | 1/3/2011 | 1/3/2011 | | PASS |
Dave Hannah
|
|
|
work in progress
|
BLD-Aging Inspection | 11/1/2010 | 11/1/2010 | 11/1/2010 | | PASS |
Dave Hannah
|
|
|
|
BLD-Conference | 9/1/2010 | 9/1/2010 | 9/1/2010 | A | PASS |
Dave Hannah
|
|
|
work in progress
|
BLD-Aging Inspection | 9/1/2010 | 9/1/2010 | 9/1/2010 | | PASS |
Dave Hannah
|
|
|
|
BLD-Conference | 6/8/2010 | 6/8/2010 | 6/8/2010 | A | PASS |
Dave Hannah
|
|
|
work in progress
|
BLD-Aging Inspection | 6/8/2010 | 6/8/2010 | 6/8/2010 | | PASS |
Dave Hannah
|
|
|
|
BLD-Conference | 4/7/2010 | 4/8/2010 | 4/8/2010 | A | PASS |
Dave Hannah
|
|
|
mike Phone #: ###-#### talked about handrails and gaurd rails
|
BLD-Aging Inspection | 2/17/2010 | 2/17/2010 | 2/17/2010 | | PASS |
Dave Hannah
|
|
|
work in progress
|
BLD-Aging Inspection | 12/18/2009 | 12/18/2009 | 12/18/2009 | | PASS |
Dave Hannah
|
|
|
work in progress
|
BLD-Energy code compliance | 11/20/2008 | 11/20/2008 | 11/20/2008 | P | PASS |
Dave Hannah
|
|
|
mike - please call 1/2 hr prior Phone #: ###-####
|
BLD-Framing/Rough-in | 10/30/2008 | 10/30/2008 | 10/30/2008 | P | PASS |
Dave Hannah
|
|
|
Mike- call 30 mins prior to going Phone #: ###-####
|
BLD-Energy code compliance | 7/2/2008 | 7/7/2008 | 7/7/2008 | P | PASS |
Dave Hannah
|
|
|
Mike- call 30 min prior Phone #: ###-#### ok to cover
|
BLD-Framing/Rough-in | 6/30/2008 | 7/2/2008 | 7/3/2008 | P | PASS |
Dave Hannah
|
|
|
Mid to late afternoon if possible please and call 30 min prior to going Mike Phone #: ###-#### ok to insulate
|
BLD-Conference | 4/21/2008 | 4/22/2008 | 4/22/2008 | A | PASS |
Dave Hannah
|
|
|
mike Note: please call 1/2 hr prior to conference late as possible Phone #: ###-####
|
BLD-Concrete | 12/26/2007 | 12/26/2007 | 12/26/2007 | P | PASS |
Dave Hannah
|
|
|
Mike PLEASE CALL 15 MIN BEFORE GOING OUT Phone #: ###-#### ok to grout cmu
|
BLD-Footing | 11/15/2007 | 11/15/2007 | 11/16/2007 | P | PASS |
Dave Hannah
|
|
|
mike Note: late afternoon please contact to meet prior to inspection Phone #: ###-####
|