BLD-Final | 4/29/2008 | 4/29/2008 | 4/29/2008 | A | PASS |
Dave Hannah
|
|
|
ERV Phone #: ###-#### ok for perm occ
|
BLD-Final | 4/25/2008 | 4/28/2008 | 4/29/2008 | P | CANC |
Dave Hannah
|
|
|
ERV Phone #: ###-####
|
Code Occupancy Approval | | | 4/28/2008 | | DONE |
|
|
|
Exterior and planter landscaping meets requirements for this bld permit
|
FIRE-Final Inspection | 4/25/2008 | 4/25/2008 | 4/25/2008 | P | PASS |
Forrest France
|
|
|
Corrections are finished, fire life safety passed final inspection.
|
FIRE-Final Inspection | 4/23/2008 | 4/24/2008 | 4/24/2008 | A | FAIL |
Forrest France
|
|
|
Need to repair exit discharge lights at the east and west sides, one EM light at the womens restroom is not functional, missing permit final for project related fire sprinkler work.
|
BLD-Framing/Rough-in | 4/14/2008 | 4/14/2008 | 4/14/2008 | P | PART |
Dave Hannah
|
|
|
erv Phone #: ###-#### ok to start covering ceiling
|
BLD-Wall cover | 4/10/2008 | 4/10/2008 | 4/10/2008 | P | PART |
Dave Hannah
|
|
|
Erv, ceiling grid inspection; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt grid ok but need to patch fire proofing on beams ok to start laying tiles
|
BLD-Energy code compliance | 1/30/2008 | 1/31/2008 | 1/31/2008 | P | PASS |
Dave Hannah
|
|
|
erv - insulation Phone #: ###-#### ok to cover ext walls
|
BLD-Framing/Rough-in | 1/24/2008 | 1/25/2008 | 1/25/2008 | A | PART |
Dave Hannah
|
|
|
Erv ###-#### ok to one side walls needs approved plans on site and elec r/i
|
BLD-Concrete | 1/15/2008 | 1/16/2008 | 1/16/2008 | A | PASS |
Dave Hannah
|
|
|
erv - rebar Phone #: ###-####
|