*(Holland & Hart)** (Suite 1200)To remodel an existing 8481 sq ft office space located on the 12th floor per approved plans. The remaining 3489 sq ft is permitted in conjunction with this permit under BLD07-02947. The area of the entire 12th story is about 14,520 square feet. The area of the lobby is approximately 2,630 sq ft the lobby was upgraded under BLD07-02000. Work is to include, construction of interior nonbearing noncombustible partitions, installation of new suspended ceilings and related lighting, to create new office spaces, conference rooms, reception areas, hallways, breakroom, and file storage areas, all related interior finishes, reducting of entire area connecting to existing HVAC System, all per the approved drawings. The fire sprinkler system, fire alarm system, and high-rise life safety systems (and the infrastructure supporting these systems) for the 12th floor are regulated under the provisions of the 2000 IBC. These systems shall be upgraded throughout the entire floor to comply with current standards unless they are already compliant. If not already existing, fire-safing shall be installed at the perimeter of the 12th floor between the floor and the spandrel glass.This building is fire sprinklered because it is a high-rise. The restrooms were previously upgraded under Bld02-00731. A SEPARATE PERMIT WILL BE REQUIRED FOR INSTALLATION AND MODIFICATION TO THE SPRINKLER SYSTEM AND ALARM SYSTEM. RmH
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final4/10/20084/10/20084/10/2008PPASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 4/10/2008 at 8:03:33 AM. Contact: ###-####. ok for perm occ
FIRE-Final Inspection4/10/20084/10/20084/10/2008PPASS
DetailsForrest France
Fire life safety inspection passed per KR.
FIRE-Final Inspection2/28/20082/29/20082/29/2008ANR
DetailsForrest France
Scheduled by a contractor via Hello! on 2/28/2008 at 2:37:41 PM. Contact: ###-####.
BLD-Final2/28/20082/29/20082/29/2008PNR
DetailsDave Hannah
Scheduled by a contractor via Hello! on 2/28/2008 at 2:38:21 PM. Contact: ###-####.
BLD-Framing/Rough-in1/23/20081/24/20081/24/2008APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 1/23/2008 at 1:06:26 PM. Contact: ###-####. ceilling ok still need minaral fire saffing to fill void to sparanel glazing and not firberglass insulation.
BLD-Framing/Rough-in1/15/20081/15/20081/15/2008PPART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 1/15/2008 at 8:28:27 AM. Contact: ###-####. conf room ceiling ok to cover
BLD-Framing/Rough-in12/28/200712/28/200712/31/2007PPART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 12/28/2007 at 10:20:25 AM. Contact: ###-####.fire blocking in floors in conf rooms ok ok to cover walls
BLD-Framing/Rough-in12/19/200712/20/200712/20/2007APART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 12/19/2007 at 3:05:49 PM. Contact: ###-####. ok to cover walls all but for conf room and plumbing wall in break room