BLD-Final | 12/3/2009 | 12/3/2009 | 12/3/2009 | P | PASS |
Tom Arcoraci
|
|
|
Barbara-everyone has signed off just waiting on youso I can issue Perm Occ-Barb Phone #: ###-####
|
BLD-Final | 12/1/2009 | 12/2/2009 | 12/2/2009 | P | PASS |
Tom Arcoraci
|
|
|
Mark Senteno with the fire dept has approved hydrant location 'as is'. Please final if no other outstanding issues.
|
FIRE-Final Inspection | 12/1/2009 | 12/2/2009 | 12/2/2009 | A | PASS |
Troy Cobbley
|
|
|
Mark Senteno with the fire dept has approved hydrant location 'as is'. Please final if no other outstanding issues. The exit sign has been provided as per the previous correction notice. No signoff card on site. Life safety passed.
|
BLD-Conference | 10/19/2009 | 10/19/2009 | 10/19/2009 | P | FAIL |
Tom Arcoraci
|
|
|
needs fire dept approval
|
BLD-Aging Inspection | 10/19/2009 | 10/19/2009 | 10/19/2009 | | FAIL |
Tom Arcoraci
|
|
|
|
BLD-Aging Inspection | 6/17/2009 | 6/17/2009 | 6/18/2009 | | NR |
Troy Cobbley
|
|
|
I spoke to Petra Construction and was deferred to Jim Hibler. A follow up inspection has been set up for one week from now.
|
BLD-Aging Inspection | 4/15/2009 | 4/15/2009 | 4/15/2009 | | NR |
Forrest France
|
|
|
See previous correction notice items.
|
BLD-Conference | 2/4/2009 | 2/4/2009 | 2/4/2009 | P | CANC |
Tom Arcoraci
|
|
|
|
BLD-Final | 11/21/2008 | 11/21/2008 | 11/21/2008 | P | NR |
Tom Arcoraci
|
|
|
|
FIRE-Final Inspection | 11/20/2008 | 11/21/2008 | 11/21/2008 | A | FAIL |
Forrest France
|
|
|
Missing one exit sign at the truckers lounge per red line annotation on approved building plan set, also missing the second fire hydrant as required per review note #3 and plan resubmittal sheet SD 1.0.
|
BLD-Final | 11/20/2008 | 11/21/2008 | 11/21/2008 | A | NR |
Tom Arcoraci
|
|
|
jc Phone #: ###-####
|
BLD-Framing/Rough-in | 11/6/2008 | 11/6/2008 | 11/6/2008 | P | PASS |
Tom Arcoraci
|
|
|
gene - ceiling grid for cover Phone #: ###-####
|
BLD-Framing/Rough-in | 11/4/2008 | 11/4/2008 | 11/4/2008 | P | PASS |
Tom Arcoraci
|
|
|
jean Phone #: ###-####
|
BLD-Framing/Rough-in | 10/20/2008 | 10/20/2008 | 10/20/2008 | P | PASS |
Jim Sly
|
|
|
gene Phone #: ###-####
|
BLD-Footing | 9/26/2008 | 9/29/2008 | 9/29/2008 | A | PASS |
Dave Hannah
|
|
|
lynn - stemwall Phone #: ###-####
|
BLD-Footing | 9/24/2008 | 9/25/2008 | 9/25/2008 | A | PART |
Jim Sly
|
|
|
Lynn Phone #: ###-#### Footing at N. E. Bldg addition OK pending MTI insp, tests and approvals.
|
BLD-Foundation | 9/9/2008 | 9/10/2008 | 9/10/2008 | A | PART |
Jim Sly
|
|
|
Lynn Phone #: ###-#### West foundation wall OK pending MTI inspection tests and approvals.
|
BLD-Footing | 9/9/2008 | 9/9/2008 | 9/9/2008 | P | PART |
Jim Storey
|
|
|
Lynn Phone #: ###-#### placed w si
|