Permit Information
Permit NumberBLD07-03136
StatusFinaled
Name CM COMPANY
Site Address 2083 E HOSPITALITY LN
Project NameSt. Lukes Family Health
Customer Number 
ePlanReviewNo
Description
St. Lukes Family Health at Hospitality Lane (Shell Only) - To construct a new 9,260 square foot, one story, wood framed medical office building and related site improvements. This shell building will have two future tenant spaces. A 6,965 square foot medical office tenant space is being constructed on the east side of this building under BLD07-03137. The second tenant space, on the west to be finished at a future date under a separate permit. This is a shell permit only and no occupancy is allowed under this permit. All construction per the approved plans and attached comment list. JCM Referance ESC07-01474 for esc informationPer Steve Webb ok to use this existing permit.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection1/23/20091/23/20091/23/2009 PASS
DetailsJim Storey
DOC - Permit Finaled1/23/20091/23/20091/23/2009PPASS
DetailsJim Storey
BLD-Final8/6/20088/7/20088/7/2008APASS
DetailsJim Storey
dan Phone #: ###-####
Code Occupancy Approval  8/6/2008 DONE
Required parking lot striping completed 8/6/08- ok for ESC permit completion- Project Manager will bring in card for signature
BLD-Final7/30/20088/1/20088/1/2008APART
DetailsJim Storey
jim Phone #: ###-#### temp ok
FIRE-Final Inspection7/29/20087/30/20087/30/2008APASS
DetailsTroy Cobbley
Life safety passed
FIRE-Final Inspection7/25/20087/25/20087/25/2008PNR
DetailsForrest France
BLD-Energy code compliance7/16/20087/17/20087/17/2008APASS
DetailsJim Storey
Dan Phone #: ###-#### vapor barrior in place above ceilling and ok to place tile.
BLD-Other7/7/20087/8/20087/8/2008APART
DetailsJim Storey
Dan- ceiling Phone #: ###-#### pending vapor barrior instal to roof deck.
BLD-Energy code compliance5/12/20085/13/20085/13/2008APART
DetailsJim Storey
dan Phone #: ###-####
BLD-Energy code compliance5/12/20085/12/20085/12/2008PNR
DetailsJim Storey
dan Phone #: ###-####
BLD-Energy code compliance5/9/20085/9/20085/9/2008PFAIL
DetailsJim Storey
dan Phone #: ###-####
BLD-Framing/Rough-in5/9/20085/9/20085/9/2008PPASS
DetailsJim Storey
dan Phone #: ###-#### c/n made ok
BLD-Energy code compliance5/8/20085/9/20085/9/2008AFAIL
DetailsJim Storey
dan Phone #: ###-####
BLD-Conference4/8/20084/8/20084/8/2008PPART
DetailsJim Storey
dan Phone #: ###-#### pending arch. drawnings.
BLD-Other4/2/20084/3/20084/3/2008PPASS
DetailsJim Storey
dan Note: roof nailing Phone #: ###-####
BLD-Other2/21/20082/21/20082/21/2008PPASS
DetailsJim Storey
dan Note: rebar stem wall Phone #: ###-#### si on site will review reports as received.
BLD-Footing2/15/20082/19/20082/19/2008APASS
DetailsJim Storey
dan Phone #: ###-#### si pending rfi to strucral engineer as to emt in footting.