BLD-Final | 4/30/2008 | 5/1/2008 | 5/1/2008 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 4/30/2008 at 10:04:41 PM. Contact: ###-####.
|
FIRE-Final Inspection | 4/30/2008 | 5/1/2008 | 5/1/2008 | A | PASS |
Forrest France
|
|
|
Noted corrections have been completed with the exception of several interior doors yet to be installed-this item can be verified at structural inspection per discussion, temporary suite address is posted until permanent signage is delivered.
|
BLD-Final | 4/29/2008 | 4/30/2008 | 5/1/2008 | P | NR |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 4/29/2008 at 11:12:08 AM. Contact: ###-####. needs fire finals
|
FIRE-Final Inspection | 4/29/2008 | 4/30/2008 | 4/30/2008 | P | FAIL |
Forrest France
|
|
|
Need to post suite address, missing required fire extinguisher per code review notes, the project related fire alarm permit must be finaled prior to life safety approval, noted several interior doors are not yet installed-hardware to be used does not appear to meet IFC 1008.1.8.1.
|
FIRE-Alarm Testing | 4/29/2008 | 4/30/2008 | 4/30/2008 | P | FAIL |
Forrest France
|
|
|
Need project related fire alarm permit requested for inspection and final.
|
FIRE-Final Inspection | 4/18/2008 | 4/18/2008 | 4/18/2008 | P | NR |
Forrest France
|
|
|
Project is not in condition for final at this time, also need related fire alarm permit finaled prior to life safety approval.
|
BLD-Other | 4/6/2008 | 4/7/2008 | 4/7/2008 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 4/6/2008 at 5:16:17 PM. Contact: ###-####. ok to cover ceiling
|
BLD-Wall cover | 3/12/2008 | 3/12/2008 | 3/12/2008 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 3/12/2008 at 9:46:37 AM. Contact: ###-####.
|
BLD-Energy code compliance | 3/6/2008 | 3/6/2008 | 3/6/2008 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 3/6/2008 at 8:28:14 AM. Contact: ###-####. ok to cover walls
|
BLD-Framing/Rough-in | 3/3/2008 | 3/4/2008 | 3/4/2008 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 3/3/2008 at 2:15:43 PM. Contact: ###-####.
|