BLD-Final | 11/25/2008 | 11/25/2008 | 11/25/2008 | P | PASS |
Jim Storey
|
|
|
c/n made ok
|
DOC - Permit Finaled | 11/25/2008 | 11/25/2008 | 11/25/2008 | P | PASS |
Jim Storey
|
|
|
|
BLD-Final | 11/13/2008 | 11/17/2008 | 11/17/2008 | A | FAIL |
Mike Jordan
|
|
|
kathy Phone #: ###-####. top of handrail being used for top of guardrail, not 36 inches high. Also remainder of handrail not 34 to 38 inches high. Called Kathy to inform her of non conformance. Customer was very rude on phone.
|
BLD-Final | 11/3/2008 | 11/4/2008 | 11/4/2008 | A | FAIL |
Mike Jordan
|
|
|
Needs to install guard rails on stairs in backyard from main level unit and provide 36 inch high guard rail around stairs going to downstairs unit.
|
BLD-Final | 10/31/2008 | 11/3/2008 | 11/3/2008 | P | NR |
Mike Jordan
|
|
|
Kathy ###-#### please call 30 min prior to arrange for access
|
BLD-Final | 11/3/2008 | 11/3/2008 | 11/3/2008 | A | CANC |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 8/7/2008 | 8/8/2008 | 8/8/2008 | A | PASS |
Mike Jordan
|
|
|
Eric- ceiling Phone #: ###-####. 2nd. layer 5/8 type x at floor ceiling assembly ok. 1hr. bearing wall ok. ok to cover.
|
BLD-Concrete | 8/4/2008 | 8/4/2008 | 8/4/2008 | P | CANC |
Mike Jordan
|
|
|
Eric- ceiling Phone #: ###-####
|
BLD-Framing/Rough-in | 8/4/2008 | 8/4/2008 | 8/4/2008 | P | PART |
Mike Jordan
|
|
|
Eric- ceiling Phone #: ###-####. 1st. layer of 5/8 type x for floor ceiling assembly.
|
BLD-Energy code compliance | 7/30/2008 | 7/30/2008 | 7/30/2008 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 7/30/2008 | 7/30/2008 | 7/30/2008 | P | PASS |
Mike Jordan
|
|
|
Eric Phone #: ###-####
|
BLD-Conference | 7/29/2008 | 7/29/2008 | 7/29/2008 | P | DONE |
Mike Jordan
|
|
|
eric Phone #: ###-####. Went over 1hr floor ceiling requirements with contractor.
|
BLD-Conference | 7/29/2008 | 7/29/2008 | 7/29/2008 | P | DONE |
Jim Sly
|
|
|
Met wtih Mike Jordan and framer
|
BLD-Conference | 7/28/2008 | 7/29/2008 | 7/29/2008 | A | CANC |
Mike Jordan
|
|
|
eric Note: please call 1/2 hr prior to conference to meet with Phone #: ###-####. rescheduled for this afternoon.
|
BLD-Framing/Rough-in | 7/25/2008 | 7/28/2008 | 7/28/2008 | A | NR |
Jim Sly
|
|
|
Eric Phone #: ###-#### Main floor locked.....went to downstair unit........called Eric.....Told him to re-call and meet insp.......issues with flr/ceil assemb.....ie.. no .Double top plates Drops.....firestopping.....etc.
|
BLD-Foundation | 5/7/2008 | 5/7/2008 | 5/7/2008 | P | PASS |
Mike Jordan
|
|
|
ben Phone #: ###-####
|
BLD-Footing | 5/5/2008 | 5/5/2008 | 5/5/2008 | P | PART |
Mike Jordan
|
|
|
ben Phone #: ###-####. wip. on footings for basement walls.
|