BLD-Final | 6/27/2008 | 6/27/2008 | 6/27/2008 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 6/27/2008 at 8:44:43 AM. Contact: ###-####. OK for Perm Occ.
|
FIRE-Final Inspection | 6/25/2008 | 6/26/2008 | 6/26/2008 | A | PASS |
Forrest France
|
|
|
Fire life safety is acceptable, exit sign locations okayed.
|
BLD-Wall cover | 6/20/2008 | 6/20/2008 | 6/20/2008 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 6/20/2008 at 7:57:34 AM. Contact: ###-####.ceiling grid ok to cover
|
BLD-Framing/Rough-in | 6/3/2008 | 6/4/2008 | 6/4/2008 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 6/3/2008 at 3:26:12 PM. Contact: ###-####.ok to cover pluming walls
|
BLD-Wall cover | 6/3/2008 | 6/3/2008 | 6/3/2008 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 6/3/2008 at 7:06:49 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 5/9/2008 | 5/9/2008 | 5/10/2008 | P | NR |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 5/8/2008 at 3:16:06 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 5/8/2008 | 5/9/2008 | 5/9/2008 | A | DEFR |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 5/8/2008 at 3:16:06 PM. Contact: ###-####.
|