Information based on query as of Friday, August 16, 2024.
Permit Information
Permit NumberBLD08-01038
StatusFinaled
Name CORNERSTONE HOMES LLC
Site Address 455 N BENJAMIN LN
Project NameFRANZ BAKERY
Customer Number 
ePlanReviewNo
Description
(FRANZ BAKERY) - Permit to Demo interior bearing walls and replace with engineered post and beam system, to construct a new accessible concrete ramp, to install new steel frame for existing overhead door in an existing CMU wall, to upgrade existing restroom to be compliant with ICC/Ansi 117.1-2003, and to relocate existing drinking fountain. This building is not fire sprinklered. A SEPARATE PERMIT WILL BE REQUIRED FOR ANY RACKING OVER EIGHT FEET HIGH. **TLW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final7/11/20087/11/20087/11/2008PPASS
DetailsMike Jordan
All issues resolved. ok for perm occ.
Code Occupancy Approval7/11/20087/11/20087/11/2008PPASS
DetailsScott M.Brown
IN COMPLIANCE WITH CZC08-00087 FOR RAMP, NO OTHER NOTED CHANGES. OK FOR FINAL.
BLD-Final7/10/20087/11/20087/11/2008ANR
DetailsMike Jordan
Scheduled by a contractor via Hello! on 7/10/2008 at 5:20:33 PM. Contact: ###-####.
BLD-Final7/8/20087/8/20087/8/2008PPART
DetailsMike Jordan
Keith Phone #: ###-####. Temp occ. granted. Needs to provide hc sign at restroom, provide vertical grab bar, mount remaining grab bars as per plan, provide flusher on toilet on clear floor space side. also needs to provide ADA compliant drinking fountain.
FIRE-Final Inspection7/7/20087/8/20087/8/2008APASS
DetailsTroy Cobbley
life safety passed.
BLD-Framing/Rough-in6/19/20086/20/20086/20/2008APART
DetailsTony Young
Scheduled by a contractor via Hello! on 6/19/2008 at 12:51:43 PM. Contact: ###-####.
new beam ok,,
FIRE-Conference6/17/20086/18/20086/19/2008ADONE
DetailsTroy Cobbley
Exit signs need to be provided at the two warehouse exterior exit doors. Emergency lights at these two doors is optional. The two doors between the offices and warehouse can be secured to prevent warehouse access to the offices. The east exit door from the showroom needs to have single action hardware and the keyed hardware removed.
BLD-Footing6/18/20086/18/20086/18/2008PPASS
DetailsJim Sly
Scheduled by a contractor via Hello! on 6/18/2008 at 8:28:27 AM. Contact: ###-####.
Determined existing slab is thickened....and is the same thickness as new footing would be ....OK
BLD-Footing6/14/20086/16/20086/16/2008APART
DetailsJim Sly
Scheduled by a contractor via Hello! on 6/14/2008 at 8:43:00 AM. Contact: ###-####.
Handicap ramp concrete OK........Interior footing pads pending approval from Eng of record.....after saw cut and removal of concrete ....Contr discovered thickened slab.....Engineer to approve existing slab OK....or......Need to remove and add new footing. Contr to have paperwork on site next inspection.