BLD-Final | 7/28/2008 | 7/29/2008 | 7/29/2008 | A | PASS |
Jim Sly
|
|
|
josh Phone #: ###-#### OK for Perm Occ.
|
FIRE-Final Inspection | 7/28/2008 | 7/28/2008 | 7/28/2008 | P | PASS |
Forrest France
|
|
|
Life safety finaled.
|
FIRE-Final Inspection | 7/28/2008 | 7/28/2008 | 7/28/2008 | A | PASS |
Forrest France
|
|
|
The remainder of C/N items verified for compliance, final life safety passed.
|
FIRE-Final Inspection | 7/25/2008 | 7/25/2008 | 7/28/2008 | P | NR |
Forrest France
|
|
|
Correction notice items are not yet finished per contractor.
|
FIRE-Conference | 7/24/2008 | 7/24/2008 | 7/24/2008 | A | DONE |
Forrest France
|
|
|
On site conference regarding approved door hardware at several locations.
|
BLD-Framing/Rough-in | 6/24/2008 | 6/24/2008 | 6/24/2008 | P | PASS |
Dave Hannah
|
|
|
josh Phone #: ###-#### ok to cover walls
|
FIRE-Final Inspection | 6/23/2008 | 6/24/2008 | 6/24/2008 | A | FAIL |
Forrest France
|
|
|
Project is not in condition for final life safety at this time, construction underway, missing exit signs and emergency lights, approved door hardware is not installed, walls and doors missing at some locations, fire extinguisher to be no higher than 48" AFF, discussed general project requirements with contractor.
|
FIRE-Final Inspection | 6/20/2008 | 6/23/2008 | 6/20/2008 | A | CANC |
Forrest France
|
|
|
josh Phone #: ###-#### Inspection cancelled from web by: Alexandra Rahn
|