Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD08-01294
StatusFinaled
Name MICROSOFT CORPORATION
Site Address 401 W FRONT ST
Project NameBELLA PLAZA OFFICE BLDG
Customer Number 
ePlanReviewNo
Description
(MICROSOFT)**(Suites 401 / 500 / 600 Located on the 4th, 5th & 6th Floors)** (PARTIAL PERMIT ISSUED 6/13/08: SEE CONDITIONS STATEMENT) To remodel half of the 4th floor, 5th floor and 6th floor for a new tenant. The fourth floor will have an area of 7007 sq ft / the fith floor area is 13,721 sq ft / and the sixth floor area is 13,721 sq ft. The total occupied tenant space will be 34,449 sq ft. Work to include, structural upgrades to the sixth floor to support the load of new servers, upgrades to the roof structure to support new HVAC roof top systems, construction of new noncombustible partitions to create office spaces, conference rooms, work rooms, mens and womens accessible shower areas, construction of two new mechanical shafts to extend from roof top units to the fourth floor, install new ceiling system and related lighting, new electrical, mechanical and plumbing work, miscellaneous related interior finishes, this building is fully fire sprinklered any alterations to the sprinkler system shall be maintained per NFPA #13 as regulated by the fire department. RmH
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final1/13/20091/13/20091/13/2009PPASS
DetailsDave Hannah
Conrad-flying into town and will be here approx 9:30 am Phone #: ###-#### ok for perm occ
BLD-Final1/13/20091/13/20091/13/2009APASS
DetailsDave Hannah
Conrad-flying into town and will be here approx 9:30 am Phone #: ###-####
FIRE-Final Inspection1/12/20091/13/20091/13/2009APASS
DetailsForrest France
Fire life safety inspection passed, correction items verified for completion.
BLD-Final1/12/20091/12/20091/13/2009PNR
DetailsDave Hannah
Conrad-flying into town and will be here approx 9:30 am Phone #: ###-####
FIRE-Conference1/7/20091/7/20091/7/2009PDONE
DetailsForrest France
Regarding actions needed for permanent certificate of occupancy.
FIRE-Conference12/30/200812/30/200812/30/2008PDONE
DetailsTroy Cobbley
A fire alarm quick permit (FIR08-00732) was issued, inspected and passed for the addition of in-duct detectors at the vertical shaft between the 5th and 6th floors. It appears that the project related FIR08-00517 is still in the issued status.
BLD-Framing/Rough-in10/21/200810/21/200810/22/2008PPASS
DetailsDave Hannah
conrad Phone #: ###-#### saft ok to cover 6th floor
BLD-Framing/Rough-in10/16/200810/17/200810/20/2008PPART
DetailsDave Hannah
Scheduled via mobile device. Name: conrad Phone #: 2067936516 ok to cover ext of shaft
BLD-Final10/3/200810/3/200810/3/2008PPART
DetailsDave Hannah
per dave hannah ok for temp occ talked with forest with fire hes ok other trades ok george has a letter from contractor about shaft they will finish in next two weeks
BLD-Other9/26/20089/29/200810/1/2008APART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 9/26/2008 at 3:21:05 PM. Contact: ###-####.ok to move onto the 4th and 5th floors still need to clean up sevel areas and items
FIRE-Final Inspection9/30/20089/30/20089/30/2008PPART
DetailsForrest France
Fire life safety final pending project related fire sprinkler permit final for field ceiling tile installation at conference rooms on the 4th,5th and 6th floors. Previous c/n items are finished.
FIRE-Final Inspection9/29/20089/30/20089/30/2008AFAIL
DetailsForrest France
Need to install one additional exit sign and provide three EM lights per plan at the multipurpose room on the 4th floor, noted missing door hardware at one office 4th floor, repair one EM light at the 5th floor, repair four emergency lights at the 6th floor-one at the open office north side, one in the cable room and two at the server room.
FIRE-Final Inspection9/26/20089/26/20089/26/2008PFAIL
DetailsTroy Cobbley
This inspection was for the 4th and 5th floors only. Replace the painted sprinkler heads on the 5th floor, provide the missing canopies for all of the heads on the 4th and 5th floors, remove the "tin foil" from the heads on the 4th and 5th floors, repair the inoperative fire/smoke damper on the 4th floor, the 5th floor restroom a/v's are mounted but the walls have no paint/finish (protect from paint), main lobby exit/emergency light is broken on the 4th floor, Relocate the exit sign/emergency light in the 4th floor reception away from the pendant sprinkler head, provide exit sign/emergency lights at atleast one exit from each of the Multipurpose rooms on the 4th floor and provide an occupant load sign (90) for the 4th floor multipurpose room.
BLD-Final9/26/20089/26/20089/26/2008PFAIL
DetailsJim Storey
Dave- call 30 mins prior to going Phone #: ###-#### exit path must be complet/ floor penatrations sealed.
BLD-Framing/Rough-in9/25/20089/26/20089/26/2008APASS
DetailsMike Jordan
Conrad- 4th floor, ceiling tile Phone #: ###-####. ceiling grid 4th floor ok.
BLD-Final9/24/20089/25/20089/26/2008PNR
DetailsDave Hannah
Conrad Phone #: ###-####
FIRE-Final Inspection9/24/20089/25/20089/25/2008ANR
DetailsForrest France
Need project related fire alarm and sprinkler permit work finals prior to building life safety approval, project is not in condition for final at this time.
BLD-Framing/Rough-in9/22/20089/22/20089/22/2008PPART
DetailsDave Hannah
conrad - ceiling grid wires Phone #: ###-#### ok to cover ceiling on 5th floor
BLD-Final9/18/20089/19/20089/20/2008PPART
DetailsDave Hannah
conrad Phone #: ###-#### ok to cover ceiling also ok to occ the 6th floor
FIRE-Final Inspection9/18/20089/19/20089/19/2008APART
DetailsTroy Cobbley
The sixth floor was given a temporary for the life safety with sam rogers permission until the fire alarm issues have been taken care of and the two conference rooms which are already in the process of remodeling are done and life safety items verified.
BLD-Other9/18/20089/19/20089/19/2008AFAIL
DetailsDave Hannah
Conrad- ceiling tile Phone #: ###-####
FIRE-Final Inspection9/18/20089/19/20089/19/2008PCANC
DetailsForrest France
conrad Phone #: ###-####
BLD-Conference9/18/20089/18/20089/18/2008PCANC
DetailsDave Hannah
FIRE-Conference9/15/20089/15/20089/15/2008PDONE
DetailsForrest France
Fire life safety conference, Conrad Phone #: ###-####
BLD-Conference8/27/20088/27/20088/27/2008PDONE
DetailsDave Hannah
conrad - 11:30 Phone #: ###-#### meet at 1:30 pm on site
BLD-Conference8/25/20088/27/20088/27/2008ACANC
DetailsDave Hannah
conrad - 11:30 Phone #: ###-#### moved to 1:30 pm
BLD-Framing/Rough-in8/20/20088/20/20088/21/2008PPART
DetailsDave Hannah
conrad - 6th floor Phone #: ###-#### ok to cover walls
BLD-Framing/Rough-in8/11/20088/12/20088/13/2008PPART
DetailsDave Hannah
Conrad Phone #: ###-#### ok to cover on walls on 5th floor
BLD-Framing/Rough-in8/11/20088/12/20088/12/2008PCANC
Details
Conrad Phone #: ###-####
BLD-Framing/Rough-in8/6/20088/7/20088/7/2008APART
DetailsDave Hannah
Conrad Phone #: ###-#### holes in floor fire stopped ok to cover walls on 4th fl
BLD-Framing/Rough-in8/6/20088/6/20088/7/2008PPART
DetailsDave Hannah
conrad Note: 4th floor please call 1/2 hr prior to inspection to get in Phone #: ###-#### walls ok but needs to seal holes in floor